3718 N MOUND VIEW AVE 91604

Certificate Information: 3718 N MOUND VIEW AVE 91604

Application / Permit
25014-30000-01783
Plan Check / Job No.
B25WL03263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(35) Condo-Single Family
Work Description
Major remodeling and ground floor and 2nd floor addition to (e) 1-story S.F.D.
Permit Issued
Issued on 7/11/2025
Issuing Office
Valley
Current Status
Issued on 7/11/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/23/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 RAHEL BEYENE
Corrections Issued 5/22/2025 RAHEL BEYENE
Quality Review Completed 5/27/2025 KEN GILL
Building Plans Picked Up 6/4/2025 APPLICANT
Applicant returned to address corrections 6/17/2025 RAHEL BEYENE
Plan Check Approved 7/10/2025 RAHEL BEYENE
Issued 7/11/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/6/2025 DIANA RENTERIA
Sewer availability Cleared 6/6/2025 DIANA RENTERIA
Roof/Waste drainage to street Cleared 6/9/2025 DAVID LOPEZ
Grading Pre-Inspection Cleared 6/17/2025 RAHEL BEYENE
CPC Cleared 6/25/2025 GEORGIA SMITH
Historic Resource Verification Cleared 7/2/2025 DANIEL CORONADO
Miscellaneous Cleared 7/9/2025 DANIEL CORONADO

Contact Information

Contractor Forefront Development Inc; Lic. No.: 809468-B 20300 VENTURA STE 215      WOODLAND HILLS, CA 91364
Engineer Kia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2025 Corrections Issued CHRISTOPHE COCHRAN
Sewer 10/6/2025 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 10/14/2025 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 10/16/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 10/28/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 10/28/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/31/2025 Partial Approval MISAEL ESPARZA
Insulation 11/4/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/6/2025 Corrections Issued CHRISTOPHE COCHRAN
Insulation 11/6/2025 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 11/6/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 2/20/2026 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 3/5/2026 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/5/2026 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 3/9/2026 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 3/9/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/9/2026 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 3/12/2026 Conditional Approval RAUL OLAGI
Interior/Exterior Lathing 3/25/2026 Partial Approval CHRISTOPHE COCHRAN
Insulation 3/31/2026 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/27/2026 Approved CHRISTOPHE COCHRAN
Green Building Rough 4/27/2026 Approved CHRISTOPHE COCHRAN
Shower Pan 6/1/2026 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/4/2026 Approved CHRISTOPHE COCHRAN