16157 W ANOKA DR 90272

Certificate Information: 16157 W ANOKA DR 90272

Application / Permit
25014-30000-01691
Plan Check / Job No.
B25WL03112
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/29/2025
Issuing Office
Valley
Current Status
Issued on 5/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/17/2025 APPLICANT
Assigned to Plan Check Engineer 4/21/2025 SELLA BENYAMIN
Corrections Issued 4/25/2025 SELLA BENYAMIN
Quality Review Completed 5/1/2025 STEVEN KIM
Building Plans Picked Up 5/5/2025 APPLICANT
Refund in Progress 5/21/2025 SELENIA GARCIA
Refund Closed 5/21/2025 SELENIA GARCIA
Plan Check Approved 5/29/2025 SELLA BENYAMIN
Issued 5/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 5/6/2025 DAVID LOPEZ
Sewer availability Cleared 5/6/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 5/13/2025 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/15/2025 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 1/9/2026 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Approved BOBBY KEY
ELECTRICAL-Rough 3/17/2026 Approved BOBBY KEY
Structural Steel Frame 3/17/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 3/31/2026 Conditional Approval BOBBY KEY
Green Building Rough 3/31/2026 Approved BOBBY KEY
HVAC-Rough 3/31/2026 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 3/31/2026 Approved BOBBY KEY
BUILDING-Rough-Frame 4/8/2026 Approved BOBBY KEY
HVAC-Rough 4/8/2026 Approved BOBBY KEY
Insulation 5/1/2026 Corrections Issued BOBBY KEY
Drywall Nailing 5/19/2026 Partial Approval DANIEL VERA
Insulation 6/8/2026 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/8/2026 Conditional Approval ARAM AVEDISIAN
Shower Pan 6/8/2026 Corrections Issued ARAM AVEDISIAN