5957 W 74TH ST 90045

Certificate Information: 5957 W 74TH ST 90045

Application / Permit
25014-30000-01678
Plan Check / Job No.
B25WL03080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to the front of (e) SFD and relocate garage door
Permit Issued
Issued on 6/27/2025
Issuing Office
West Los Angeles
Current Status
Issued on 6/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/16/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 REZA HAGHIGHAT
Corrections Issued 4/20/2025 REZA HAGHIGHAT
Building Plans Picked Up 4/22/2025 APPLICANT
Plan Check Approved 6/20/2025 HOOMAN HAJIZADEH
Issued 6/27/2025 APPLICANT

Permit Application Clearance Information

Permit Cleared 4/22/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 4/22/2025 XOCHITL ARQUIETA
Sewer availability Cleared 4/22/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 6/16/2025 SAFA JAVANMARDI
Trees in Parkway Cleared 6/16/2025 MIGUEL ORNELAS
GPI Written Notices Cleared 6/20/2025 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 6/20/2025 REZA HAGHIGHAT

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Architect Saadat,, Ariel Jacob; Lic. No.: C41643 6607 LINDENHURST AVE      LOS ANGELES, CA 90048
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/30/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 8/5/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Corrections Issued JESUS PINEDA
Sewer 10/7/2025 Approved JESUS PINEDA
Underground Mechanical 10/7/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 10/17/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 10/20/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 10/28/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 11/19/2025 Partial Approval JESUS PINEDA
HVAC-Rough 12/11/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 12/12/2025 Corrections Issued JESUS PINEDA
Green Building Rough 12/12/2025 Approved JESUS PINEDA
MERV13>=Rough 12/12/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/19/2025 Approved ANTHONY EGSON
Insulation 12/19/2025 Approved ANTHONY EGSON
Drywall Nailing 12/26/2025 Approved JESUS PINEDA
Shower Pan 12/26/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 1/15/2026 Approved JESUS PINEDA
ELECTRICAL-Final 3/3/2026 Approved JESUS PINEDA
Final 3/3/2026 Corrections Issued JESUS PINEDA
Green Building Final 3/3/2026 Corrections Issued JESUS PINEDA
MERV13>=Final 3/3/2026 Approved JESUS PINEDA
PLUMBING-Final 3/3/2026 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved JESUS PINEDA
Smoke Detectors 3/3/2026 Approved JESUS PINEDA