1263 N MONUMENT ST 90272

Certificate Information: 1263 N MONUMENT ST 90272

Application / Permit
25014-30000-01631
Plan Check / Job No.
B25WL02998
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/9/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2025 APPLICANT
Assigned to Plan Check Engineer 4/16/2025 SERGIO SILVA
Corrections Issued 4/24/2025 SERGIO SILVA
Quality Review Completed 4/24/2025 CHIHARU SUZUKI
Building Plans Picked Up 4/28/2025 APPLICANT
Applicant returned to address corrections 5/27/2025 SERGIO SILVA
Plan Check Approved 6/5/2025 SERGIO SILVA
Issued 6/9/2025 APPLICANT
CofO in Progress 12/29/2025 KENNETH NAGLE
Permit Finaled 12/29/2025 RICHARD STEINBACH
CofO Issued 12/29/2025 RICHARD STEINBACH
Permit Finaled 12/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/2/2025 LUIS LUVANO
BHO/Hillside ordinance Cleared 5/8/2025 JILVER MAZARIEGOS
Eng Process Fee Ord 176,300 Cleared 5/8/2025 JILVER MAZARIEGOS
Sewer availability Cleared 5/8/2025 JILVER MAZARIEGOS
Distance to fire station Cleared 5/12/2025 JOHN CONNEALLY
Hydrant and Access approval Cleared 5/12/2025 JOHN CONNEALLY
Permit Cleared 5/13/2025 JILVER MAZARIEGOS
Construction near power lines Cleared 5/14/2025 RIDWAN HARDY
Construction within easement Cleared 5/14/2025 RIDWAN HARDY
Roof/Waste drainage to street Cleared 5/19/2025 JILVER MAZARIEGOS
Miscellaneous Cleared 6/5/2025 SERGIO SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 6/13/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/25/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 6/25/2025 Approved STEPHANIE SWANSON
PLUMBING-Rough 6/25/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Partial Approval HERBERT GIRON
Deputy Steel/Welding 7/9/2025 No Access for Inspection KENNETH NAGLE
Structural Steel Frame 7/11/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 8/29/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 9/2/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 9/2/2025 Approved TEMISTOCLES CAAL
Final 9/2/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Approved TEMISTOCLES CAAL
Green Building Rough 9/2/2025 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 9/2/2025 Partial Approval TEMISTOCLES CAAL
Verify Sprinkler Sign Off 9/2/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 9/8/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 9/8/2025 Approved TEMISTOCLES CAAL
Green Building Rough 9/8/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 9/8/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 9/8/2025 Approved TEMISTOCLES CAAL
Insulation 9/10/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/12/2025 Partial Approval TEMISTOCLES CAAL
Shower Pan 9/12/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 9/17/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 9/17/2025 Approved TEMISTOCLES CAAL
Gas Test 9/25/2025 Not Ready for Inspection JAYLIN GRAVITTE
Gas Test 9/29/2025 Approved TEMISTOCLES CAAL
Pre-Inspection 10/24/2025 Partial Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 10/31/2025 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Final 11/19/2025 Approved TEMISTOCLES CAAL
Final 11/19/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Final 11/19/2025 Approved TEMISTOCLES CAAL
HVAC-Final 11/19/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 11/19/2025 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 11/19/2025 SGSOV Approved TEMISTOCLES CAAL
Service/Power Release 11/19/2025 Approved TEMISTOCLES CAAL
Smoke Detectors 11/19/2025 Approved TEMISTOCLES CAAL
Pre-Inspection 12/1/2025 Partial Inspection TEMISTOCLES CAAL
Final 12/29/2025 OK to Issue CofO KENNETH NAGLE