1126 N MONUMENT ST 90272

Certificate Information: 1126 N MONUMENT ST 90272

Application / Permit
25014-30000-01585
Plan Check / Job No.
B25WL02919
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, BASEMENT AND PATIO COVER, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 6/24/2025
Issuing Office
Metro
Current Status
Issued on 6/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/10/2025 APPLICANT
Assigned to Plan Check Engineer 4/11/2025 KEVIN MORALES
Corrections Issued 4/16/2025 KEVIN MORALES
Quality Review Completed 4/21/2025 EUGENE BARBEAU
Building Plans Picked Up 4/23/2025 APPLICANT
Plan Check Approved 6/24/2025 KEVIN MORALES
Issued 6/24/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/17/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 4/17/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 4/22/2025 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/4/2025 Conditional Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 11/24/2025 Partial Approval BOBBY KEY
Deputy Reinf. Concrete 11/25/2025 Conditional Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/3/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/24/2025 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 12/31/2025 Corrections Issued DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/8/2026 Not Ready for Inspection STEPHANIE SWANSON
Pre-Inspection 2/27/2026 Partial Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 3/12/2026 Corrections Issued HERBERT GIRON
Deputy Wood Construction 3/13/2026 Conditional Approval JUAN VALENZUELA
Shower Pan 3/13/2026 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/17/2026 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 3/18/2026 Partial Approval TEMISTOCLES CAAL
Shower Pan 3/18/2026 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 3/27/2026 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 3/27/2026 Approved MICHAEL ALLEN
HVAC-Rough 3/31/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/6/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 5/27/2026 Approved MICHAEL ALLEN
Verify Sprinkler Sign Off 5/27/2026 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 6/1/2026 Approved TEMISTOCLES CAAL
Green Building Rough 6/1/2026 Approved TEMISTOCLES CAAL