1003 N BIENVENEDA AVE 90272
Certificate Information: 1003 N BIENVENEDA AVE 90272
- Application / Permit
- 25014-30000-01547
- Plan Check / Job No.
- B25WL02812
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 7/14/2025
- Issuing Office
- Current Status
- Issued on 7/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2025 | SERGIO SILVA |
| Corrections Issued | 4/18/2025 | SERGIO SILVA |
| Quality Review Completed | 4/18/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/21/2025 | APPLICANT |
| Applicant returned to address corrections | 6/13/2025 | SERGIO SILVA |
| Applicant returned to address corrections | 7/7/2025 | SERGIO SILVA |
| Plan Check Approved | 7/14/2025 | SERGIO SILVA |
| Issued | 7/14/2025 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/3/2025 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2025 | KEVIN CHUNG |
| Sewer availability | Cleared | 6/3/2025 | KEVIN CHUNG |
| Distance to fire station | Cleared | 6/23/2025 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 6/23/2025 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 6/26/2025 | MARTIN FRAGOSO |
| Permit | Cleared | 7/7/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 7/7/2025 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 7/7/2025 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | R B Construction; Lic. No.: 540333-B | 1473 CALLE VIOTETA THOUSAND OAKS, CA 91360 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 6/16/2026 |
| Smoke Detectors | 6/16/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 |
| Green Building Final | 6/16/2026 |
Inspection Request History
| PLUMBING-Rough | 7/17/2025 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/23/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 9/2/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/2/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/2/2025 | Corrections Issued | BOBBY KEY |
| Verify Sprinkler Sign Off | 9/2/2025 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 9/9/2025 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 9/16/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/19/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 9/19/2025 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 9/19/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/19/2025 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 9/19/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/23/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 9/23/2025 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 9/23/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 9/30/2025 | Conditional Approval | BOBBY KEY |
| Drywall Nailing | 10/7/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/16/2025 | Approved | BOBBY KEY |
| Gas Test | 2/2/2026 | Approved | DANIEL VERA |
| Underground Mechanical | 2/2/2026 | Partial Approval | DANIEL VERA |
| Gas Test | 2/3/2026 | Approved | DANIEL VERA |