13007 W DEWEY ST 90066
Certificate Information: 13007 W DEWEY ST 90066
- Application / Permit
- 25014-30000-01497
- Plan Check / Job No.
- B25WL02688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) Attached carport. Per engineering design.
- Permit Issued
- Issued on 4/25/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2025 | ALFREDO JARA |
| Corrections Issued | 4/6/2025 | ALFREDO JARA |
| Building Plans Picked Up | 4/9/2025 | APPLICANT |
| Plan Check Approved | 4/21/2025 | HOOMAN HAJIZADEH |
| Issued | 4/25/2025 | APPLICANT |
| CofO in Progress | 10/1/2025 | WILBER ROSALES |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
| CofO Issued | 10/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2025 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 4/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/10/2025 | BIAINA HARITUNIAN |
| Specific Plan | Cleared | 4/17/2025 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 4/21/2025 | ALFREDO JARA |
Contact Information
| Contractor | Riviera Development Partners Llc; Lic. No.: 1133309-B | 23 CORPORATE PLAZA DR 150 NEWPORT BEACH, CA 92660 |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 5/13/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/13/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Drywall Nailing | 5/19/2025 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 5/19/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/19/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Corrections Issued | MICHAEL ALLEN |
| Deputy Steel/Welding | 8/4/2025 | Conditional Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 8/13/2025 | Not Ready for Inspection | WILBER ROSALES |
| Final | 8/13/2025 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 8/13/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 8/13/2025 | Approved | WILBER ROSALES |
| Smoke Detectors | 8/13/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | WILBER ROSALES |
| Final | 9/5/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Final | 9/30/2025 | Approved | WILBER ROSALES |
| Final | 9/30/2025 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 9/30/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 9/30/2025 | Approved | WILBER ROSALES |