1844 S ARMACOST AVE 90025
Certificate Information: 1844 S ARMACOST AVE 90025
- Application / Permit
- 25014-30000-01374
- Plan Check / Job No.
- B25WL02486
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior and exterior remodel and ground floor addition to (E) 1-story SFD
- Permit Issued
- Issued on 6/9/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2025 | DAVID CASTILLO |
| Corrections Issued | 4/2/2025 | DAVID CASTILLO |
| Building Plans Picked Up | 4/3/2025 | APPLICANT |
| Plan Check Approved | 4/23/2025 | BEHROUZ KHOKHAR |
| Issued | 6/9/2025 | APPLICANT |
| CofO in Progress | 10/17/2025 | KENNETH NAGLE |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
| CofO Issued | 10/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/5/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2025 | DARIN LAM |
| Sewer availability | Cleared | 4/18/2025 | DARIN LAM |
Contact Information
| Contractor | M L N Builders Inc; Lic. No.: 1054900-B | 7234 BELLAIRE AVE NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Pre-Inspection | 6/12/2025 | Partial Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 6/13/2025 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 6/13/2025 | Conditional Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/17/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 6/17/2025 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 6/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 6/24/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 6/27/2025 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 6/27/2025 | Approved | KIRK SANDERS |
| Wood Frame | 6/27/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/30/2025 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Wood Construction | 6/30/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 6/30/2025 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 6/30/2025 | Approved | KIRK SANDERS |
| Special/Order Compliance | 6/30/2025 | Corrections Issued | KIRK SANDERS |
| Wood Frame | 6/30/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/1/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 7/1/2025 | Conditional Approval | KIRK SANDERS |
| Insulation | 7/1/2025 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 7/1/2025 | Approved | KIRK SANDERS |
| Insulation | 7/3/2025 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 7/3/2025 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 8/1/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Rough | 8/1/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/5/2025 | Approved | TEMISTOCLES CAAL |
| Final | 9/19/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/19/2025 | Approved | ARAM AVEDISIAN |
| Green Building Final | 9/19/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 9/19/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 10/3/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 10/3/2025 | Approved | ARAM AVEDISIAN |
| Final | 10/17/2025 | OK to Issue CofO | KENNETH NAGLE |