7838 S TRUXTON AVE 90045

Certificate Information: 7838 S TRUXTON AVE 90045

Application / Permit
25014-30000-01321
Plan Check / Job No.
B25WL02332
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition of 1st floor, remodel existing area. New 2nd floor addition with an attached new car garage to existing one story SFD.
Permit Issued
Issued on 7/1/2025
Issuing Office
West Los Angeles
Current Status
Issued on 7/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/25/2025 APPLICANT
Assigned to Plan Check Engineer 4/10/2025 ZENA HADDIS
Corrections Issued 4/29/2025 ZENA HADDIS
Quality Review Completed 4/30/2025 CHIHARU SUZUKI
Building Plans Picked Up 5/2/2025 APPLICANT
Plan Check Approved 7/1/2025 ZENA HADDIS
Issued 7/1/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/28/2025 LIAM ODONOVAN
Sewer availability Cleared 4/28/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 6/23/2025 LIAM ODONOVAN
Grading Pre-Inspection Cleared 7/1/2025 ZENA HADDIS

Contact Information

Contractor Owner-Builder       ,
Engineer Habibi,, Shayaan; Lic. No.: C94225 10535 WILSHIRE BLVD APT 1602      LOS ANGELES, CA 90024

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/8/2025 Partial Approval HERBERT GIRON
Special/Order Compliance 8/8/2025 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 8/18/2025 Approved JESUS PINEDA
Deputy Reinf. Concrete 8/21/2025 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 9/11/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 11/20/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 12/9/2025 Approved JESUS PINEDA
Sewer 12/9/2025 Approved JESUS PINEDA
Underground Mechanical 12/9/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 3/11/2026 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/27/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/1/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/17/2026 Partial Approval JESUS PINEDA
Green Building Rough 4/17/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 4/17/2026 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 4/17/2026 Approved JESUS PINEDA
Shower Pan 4/23/2026 Approved JESUS PINEDA
Insulation 5/15/2026 Corrections Issued MICHAEL LEWIS
Insulation 5/22/2026 Approved MICHAEL LEWIS
Drywall Nailing 6/3/2026 Approved MICHAEL LEWIS