3253 S INGLEWOOD BLVD 90066
Certificate Information: 3253 S INGLEWOOD BLVD 90066
- Application / Permit
- 25014-30000-01317
- Plan Check / Job No.
- B25WL02318
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY SFD WITH ATTACHED GARAGE -BLDG SPRINKLRED THRU-OUT
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Metro
- Current Status
- Issued on 8/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/25/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 4/17/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 4/21/2025 | KEN GILL |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Plan Check Approved | 8/15/2025 | MAHNAZ NOURHASHEMI |
| Issued | 8/18/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/29/2025 | RICHARD WOO |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/30/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/30/2025 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 6/17/2025 | LAVEON RIDER |
| Excavation more than 5-ft deep | Cleared | 8/15/2025 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 8/15/2025 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 8/15/2025 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/9/2025 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 9/9/2025 | Not Ready for Inspection | KIRK SANDERS |
| Special/Order Compliance | 9/9/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/17/2025 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 9/29/2025 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 10/3/2025 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 10/3/2025 | Corrections Issued | KIRK SANDERS |
| Sewer | 10/6/2025 | Partial Approval | KIRK SANDERS |
| Underground Mechanical | 10/6/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/8/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/28/2025 | Corrections Issued | KIRK SANDERS |
| Deputy Drilled-In Anchors | 10/28/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Conditional Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/28/2025 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 1/2/2026 | Conditional Approval | DAVID FEILER |
| Deputy Wood Construction | 1/28/2026 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2026 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 3/17/2026 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/17/2026 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 3/19/2026 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Partial Approval | EVAN COOPER |
| Green Building Rough | 3/24/2026 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 3/24/2026 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/24/2026 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/24/2026 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/13/2026 | Approved | EVAN COOPER |
| Green Building Rough | 4/13/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/13/2026 | Partial Approval | EVAN COOPER |
| Insulation | 4/21/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/24/2026 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 4/24/2026 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 5/1/2026 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/29/2026 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 5/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 6/9/2026 | Approved | KIRK SANDERS |
| Gas Test | 6/15/2026 | Not Ready for Inspection | KIRK SANDERS |