1612 S SHERBOURNE DR 90035
Certificate Information: 1612 S SHERBOURNE DR 90035
- Application / Permit
- 25014-30000-01126
- Plan Check / Job No.
- B25WL01966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major alteriation and addtion to an (E) Single family dwelling to create a new 2-Story Single Family Dwelling w/ attached garage. Fully sprinkled NFPA 13-D
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 8/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2025 | EDWIN ESPIN |
| Corrections Issued | 3/27/2025 | EDWIN ESPIN |
| Quality Review Completed | 4/9/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/14/2025 | APPLICANT |
| Applicant returned to address corrections | 6/27/2025 | EDWIN ESPIN |
| Plan Check Approved | 8/12/2025 | ZENA HADDIS |
| Issued | 8/14/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/1/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 5/8/2025 | CELINA MORENO |
| Trees in Parkway | Cleared | 8/1/2025 | MIGUEL ORNELAS |
Contact Information
| Architect | Davis,, Lisa M; Lic. No.: C27408 | 3242 MALCOLM AVENUE LOS ANGELES, CA 90034 |
| Contractor | Home Care & Design Inc; Lic. No.: 960851-B | 1976 S LA CIENEGA BLVD #225 LOS ANGELES, CA 90034 |
| Engineer | Lotfi,, Fariborz F; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Sanchez,, Carlos Gabriel; Lic. No.: L9120 | 228 E LIME AVE MONROVIA, CA 91016 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 9/17/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 9/17/2025 | Partial Approval | EVAN COOPER |
| Sewer | 9/17/2025 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 9/25/2025 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 9/25/2025 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 10/3/2025 | Approved | EVAN COOPER |
| METHANE-Barrier | 10/3/2025 | Approved | EVAN COOPER |
| Structural Steel Frame | 10/3/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2026 | Approved | WILBER ROSALES |
| HVAC-Rough | 2/19/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 3/3/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 3/3/2026 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 4/21/2026 | Not Ready for Inspection | WILBER ROSALES |
| Interior/Exterior Lathing | 4/21/2026 | Not Ready for Inspection | WILBER ROSALES |
| METHANE-Rough | 4/21/2026 | Not Ready for Inspection | WILBER ROSALES |
| Shower Pan | 4/21/2026 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 5/15/2026 | Partial Approval | WILBER ROSALES |
| Deputy Shotcrete | 5/19/2026 | Conditional Approval | BOBBY KEY |