1612 S SHERBOURNE DR 90035

Certificate Information: 1612 S SHERBOURNE DR 90035

Application / Permit
25014-30000-01126
Plan Check / Job No.
B25WL01966
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major alteriation and addtion to an (E) Single family dwelling to create a new 2-Story Single Family Dwelling w/ attached garage. Fully sprinkled NFPA 13-D
Permit Issued
Issued on 8/14/2025
Issuing Office
West Los Angeles
Current Status
Issued on 8/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/13/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 EDWIN ESPIN
Corrections Issued 3/27/2025 EDWIN ESPIN
Quality Review Completed 4/9/2025 CHIHARU SUZUKI
Building Plans Picked Up 4/14/2025 APPLICANT
Applicant returned to address corrections 6/27/2025 EDWIN ESPIN
Plan Check Approved 8/12/2025 ZENA HADDIS
Issued 8/14/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/1/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/1/2025 BIAINA HARITUNIAN
Sewer availability Cleared 5/1/2025 BIAINA HARITUNIAN
Permit Cleared 5/8/2025 CELINA MORENO
Trees in Parkway Cleared 8/1/2025 MIGUEL ORNELAS

Contact Information

Architect Davis,, Lisa M; Lic. No.: C27408 3242 MALCOLM AVENUE      LOS ANGELES, CA 90034
Contractor Home Care & Design Inc; Lic. No.: 960851-B 1976 S LA CIENEGA BLVD #225      LOS ANGELES, CA 90034
Engineer Lotfi,, Fariborz F; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Sanchez,, Carlos Gabriel; Lic. No.: L9120 228 E LIME AVE      MONROVIA, CA 91016

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 9/17/2025 Approved EVAN COOPER
PLUMBING-Rough 9/17/2025 Partial Approval EVAN COOPER
Sewer 9/17/2025 Approved EVAN COOPER
Footing/Foundation/Slab 9/25/2025 Partial Approval EVAN COOPER
METHANE-Barrier 9/25/2025 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 10/3/2025 Approved EVAN COOPER
METHANE-Barrier 10/3/2025 Approved EVAN COOPER
Structural Steel Frame 10/3/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/19/2026 Approved WILBER ROSALES
HVAC-Rough 2/19/2026 Approved WILBER ROSALES
ELECTRICAL-Rough 3/3/2026 Approved WILBER ROSALES
PLUMBING-Rough 3/3/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/21/2026 Not Ready for Inspection WILBER ROSALES
Interior/Exterior Lathing 4/21/2026 Not Ready for Inspection WILBER ROSALES
METHANE-Rough 4/21/2026 Not Ready for Inspection WILBER ROSALES
Shower Pan 4/21/2026 Approved WILBER ROSALES
Interior/Exterior Lathing 5/15/2026 Partial Approval WILBER ROSALES
Deputy Shotcrete 5/19/2026 Conditional Approval BOBBY KEY