3153-3155 S PURDUE AVE 90066

Certificate Information: 3153-3155 S PURDUE AVE 90066

Application / Permit
25014-30000-01047
Plan Check / Job No.
B25WL01794
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Major remodel & (n) 2nd story addition & attached ADU per LAMC 12.22 A.33(c) And (e)
Permit Issued
Issued on 6/6/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2025 APPLICANT
Assigned to Plan Check Engineer 3/13/2025 ZENA HADDIS
Corrections Issued 4/10/2025 ZENA HADDIS
Quality Review Completed 4/17/2025 CHIHARU SUZUKI
Building Plans Picked Up 5/7/2025 APPLICANT
Plan Check Approved 6/6/2025 ZENA HADDIS
Issued 6/6/2025 APPLICANT
CofO in Progress 3/19/2026 ARAM AVEDISIAN
Permit Finaled 3/24/2026 RICHARD STEINBACH
CofO Issued 3/24/2026 RICHARD STEINBACH
Permit Finaled 3/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 4/26/2025 DARIN LAM
Roof/Waste drainage to street Cleared 4/26/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 4/29/2025 DARIN LAM
Sewer availability Cleared 4/29/2025 DARIN LAM
Trees in Parkway Cleared 5/15/2025 MIGUEL ORNELAS
Permit Cleared 5/19/2025 DIANA RENTERIA
Specific Plan Cleared 5/19/2025 RICHARD WOO
GPI Written Notices Cleared 5/30/2025 CHIHARU SUZUKI
Grading Pre-Inspection Cleared 5/30/2025 ZENA HADDIS

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor O & S Framing; Lic. No.: 1113108-B 1311 E AVE R3      PALMDALE, CA 93550
Engineer Azarmy,, Cyrus; Lic. No.: L9404 4402 CHARLEMONT AVE      WOODLAND HILLS, CA 91364
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/20/2025 Approved WILBER ROSALES
Excavation/Setback/Form/Re-Bar 7/5/2025 Corrections Issued DANIEL VERA
Excavation/Setback/Form/Re-Bar 7/8/2025 Corrections Issued WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 8/6/2025 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 8/6/2025 Approved BOBBY KEY
Deputy Steel/Welding 8/11/2025 Conditional Approval JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 8/21/2025 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 8/29/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 9/29/2025 Approved KIRK SANDERS
HVAC-Final 9/29/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 9/29/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 9/30/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 9/30/2025 Approved KIRK SANDERS
HVAC-Rough 9/30/2025 Approved KIRK SANDERS
PLUMBING-Final 9/30/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 9/30/2025 Conditional Approval KIRK SANDERS
Shower Pan 9/30/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/1/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 10/1/2025 Conditional Approval KIRK SANDERS
Interior/Exterior Lathing 10/6/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 10/10/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 10/10/2025 Corrections Issued KIRK SANDERS
Insulation 10/21/2025 Approved WILBER ROSALES
Drywall Nailing 10/27/2025 Partial Approval KIRK SANDERS
Drywall Nailing 10/30/2025 Approved KIRK SANDERS
PLUMBING-Final 2/26/2026 Approved RYAN SALAZAR
ELECTRICAL-Final 2/27/2026 Approved EVAN COOPER
HVAC-Final 2/27/2026 Approved EVAN COOPER
BUILDING-Rough-Frame 3/5/2026 Not Ready for Inspection ARAM AVEDISIAN
Final 3/5/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/5/2026 Approved ARAM AVEDISIAN
Green Building Rough 3/5/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/5/2026 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 3/5/2026 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/18/2026 Not Ready for Inspection ARAM AVEDISIAN
Final 3/18/2026 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 3/19/2026 Approved ARAM AVEDISIAN
Final 3/19/2026 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 3/19/2026 Approved ARAM AVEDISIAN