1126 S CREST DR 90035
Certificate Information: 1126 S CREST DR 90035
- Application / Permit
- 25014-30000-00986
- Plan Check / Job No.
- B25WL01680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached 1-story garage to ADU w/ 2nd floor addition per GC 66323(a)(4) ** 2 of 2 **
- Permit Issued
- Issued on 8/28/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 8/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2025 | DAVID CASTILLO |
| Corrections Issued | 3/11/2025 | DAVID CASTILLO |
| Quality Review Completed | 3/17/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/20/2025 | APPLICANT |
| Applicant returned to address corrections | 8/5/2025 | DAVID CASTILLO |
| Plan Check Approved | 8/15/2025 | DAVID CASTILLO |
| Issued | 8/28/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2025 | ABEL CASILLAS |
| Address approval | Cleared | 5/19/2025 | ABEL CASILLAS |
| Miscellaneous | Cleared | 6/26/2025 | ALBERT TAM |
| Miscellaneous | Cleared | 6/26/2025 | ALBERT TAM |
| Construction within easement | Cleared | 6/30/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 6/30/2025 | ABEL CASILLAS |
| Grading Pre-Inspection | Cleared | 8/5/2025 | LANNY MERRICK |
| GPI Written Notices | Cleared | 8/15/2025 | DAVID CASTILLO |
Contact Information
| Contractor | Elm Construction; Lic. No.: 1099704-B | 1976 S LA CIENEGA BLVD C-127 LOS ANGELES, CA 90034 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| HVAC-Final | 6/8/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 |
| Final | 6/8/2026 |
| PLUMBING-Final | 6/8/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 9/16/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 9/16/2025 | Partial Approval | MICHAEL ALLEN |
| Pre-Inspection | 9/16/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 9/16/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 11/12/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Partial Approval | EVAN COOPER |
| Rough-Elec/Plmb/HVAC | 11/18/2025 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 12/3/2025 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 12/3/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | EVAN COOPER |
| Rough-Elec/Plmb/HVAC | 12/3/2025 | Approved | EVAN COOPER |
| Shower Pan | 12/3/2025 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 12/3/2025 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 12/17/2025 | Approved | KIRK SANDERS |
| Insulation | 12/17/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 12/17/2025 | Partial Approval | KIRK SANDERS |
| Shower Pan | 12/17/2025 | Not Ready for Inspection | KIRK SANDERS |
| Drywall Nailing | 12/31/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/31/2025 | Approved | MICHAEL ALLEN |
| Shower Pan | 12/31/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| Gas Test | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| METHANE-Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Not Ready | WILBER ROSALES |
| Service/Power Release | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| Smoke Detectors | 3/11/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 5/15/2026 | Not Ready for Inspection | WILBER ROSALES |
| Green Building Final | 5/15/2026 | Not Ready for Inspection | WILBER ROSALES |
| METHANE-Final | 5/15/2026 | Not Ready for Inspection | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Not Ready | WILBER ROSALES |
| Smoke Detectors | 5/15/2026 | Not Ready for Inspection | WILBER ROSALES |
| Underground Mechanical | 5/15/2026 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Final | 6/1/2026 | Approved | ASHLEY THOMPSON |
| Final | 6/1/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 6/1/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 6/1/2026 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Final | 6/1/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 6/1/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Service/Power Release | 6/1/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 6/1/2026 | Approved | ASHLEY THOMPSON |