8331 S LILIENTHAL AVE 90045
Certificate Information: 8331 S LILIENTHAL AVE 90045
- Application / Permit
- 25014-30000-00967
- Plan Check / Job No.
- B25WL01631
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 1-story detached garage to ADU w/addition per LAMC 12.22A.33(b)(1),(c),(d),(h) and (k). All work per WFPP
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2025 | DAVID CASTILLO |
| Corrections Issued | 3/11/2025 | DAVID CASTILLO |
| Building Plans Picked Up | 3/12/2025 | APPLICANT |
| Applicant returned to address corrections | 3/21/2025 | AMY GUEVARRA |
| Plan Check Approved | 4/24/2025 | JAHANSHAH POURHASSAN |
| Issued | 4/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/13/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 3/13/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2025 | JEANIE LAM |
| Sewer availability | Cleared | 3/17/2025 | JEANIE LAM |
| ZA Case | Cleared | 3/17/2025 | YINGSHI HUANG |
| Specific Plan | Cleared | 4/22/2025 | EDER ROMERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 5/14/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 7/24/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 7/28/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Partial Approval | JESUS PINEDA |
| Sewer | 9/19/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 9/19/2025 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 9/22/2025 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 10/24/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 10/24/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/4/2026 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 2/4/2026 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/4/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/10/2026 | Approved | JESUS PINEDA |
| Green Building Rough | 2/10/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/10/2026 | Partial Approval | JESUS PINEDA |
| Insulation | 2/20/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 3/12/2026 | Approved | ANTHONY EGSON |
| Shower Pan | 3/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Special/Order Compliance | 3/12/2026 | Partial Inspection | BOBBY KEY |
| Shower Pan | 3/16/2026 | Approved | JESUS PINEDA |