23623 W LADRILLO ST 91367

Certificate Information: 23623 W LADRILLO ST 91367

Application / Permit
25014-30000-00833
Plan Check / Job No.
B25WL01376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING. CONVERT PORTION OF SFD TO SINGLE CAR GARAGE PER ENGINEERS CALCS WITH STEEL BEAM AND COLUMNS
Permit Issued
Issued on 3/11/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2025 APPLICANT
Assigned to Plan Check Engineer 2/25/2025 AMY GUEVARRA
Corrections Issued 2/25/2025 AMY GUEVARRA
Plan Check Approved 3/6/2025 HOOMAN HAJIZADEH
Issued 3/11/2025 APPLICANT
CofO in Progress 11/21/2025 GEVORK IPCHYAN
Permit Finaled 12/3/2025 JOHN JANSON
CofO Issued 12/3/2025 JOHN JANSON
Permit Finaled 12/3/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/25/2025 CARLOS RAMIREZ
Sewer availability Cleared 2/25/2025 CARLOS RAMIREZ
Trees in Parkway Cleared 2/27/2025 BRANDON WONG
Grading Pre-Inspection Cleared 2/27/2025 GERMAN RODRIGUEZ MENDOZA
Eng Process Fee Ord 176,300 Cleared 2/28/2025 EDGAR ALCARAZ
Permit Cleared 2/28/2025 EDGAR ALCARAZ

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/19/2025 Partial Approval TROY SANDERS
Footing/Foundation/Slab 4/11/2025 Partial Approval JEFFREY HARTLINE
Underground Mechanical 4/11/2025 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 4/15/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 4/16/2025 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 4/18/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 4/18/2025 Corrections Issued JEFFREY HARTLINE
Interior/Exterior Lathing 4/28/2025 Not Ready for Inspection GEVORK IPCHYAN
Deputy Reinf. Concrete 4/29/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 5/28/2025 Partial Approval GEVORK IPCHYAN
Deputy Wood Construction 5/28/2025 Conditional Approval GEVORK IPCHYAN
ELECTRICAL-Rough 5/28/2025 Not Ready for Inspection GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/28/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 5/28/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 5/28/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 6/2/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 6/2/2025 Approved GEVORK IPCHYAN
Green Building Rough 6/2/2025 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 6/2/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 6/2/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 6/4/2025 Approved GEVORK IPCHYAN
Green Building Rough 6/4/2025 Approved GEVORK IPCHYAN
Insulation 6/4/2025 Approved GEVORK IPCHYAN
Drywall Nailing 6/18/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 6/30/2025 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 7/7/2025 Partial Approval TROY SANDERS
Shower Pan 7/7/2025 Approved TROY SANDERS
Final 11/4/2025 Corrections Issued ROBERT GOLD
Green Building Final 11/4/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 11/4/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 11/4/2025 Approved ROBERT GOLD
Final 11/10/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Not Ready GEVORK IPCHYAN
Final 11/14/2025 Corrections Issued GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved GEVORK IPCHYAN
Final 11/18/2025 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Final 11/20/2025 Approved GEVORK IPCHYAN
Final 11/20/2025 OK to Issue CofO GEVORK IPCHYAN
HVAC-Final 11/20/2025 Approved GEVORK IPCHYAN
PLUMBING-Final 11/20/2025 Approved GEVORK IPCHYAN