5350 W THORNBURN ST 90045

Certificate Information: 5350 W THORNBURN ST 90045

Application / Permit
25014-30000-00534
Plan Check / Job No.
B25WL00843
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Two-car attached garage, master bedroom and bathroom addition with kitchen remodel **See comments**
Permit Issued
Issued on 5/8/2025
Issuing Office
San Pedro
Current Status
Issued on 5/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/6/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 JAHANSHAH POURHASSAN
Corrections Issued 2/17/2025 JAHANSHAH POURHASSAN
Building Plans Picked Up 2/18/2025 APPLICANT
Applicant returned to address corrections 4/16/2025 AMY GUEVARRA
Applicant returned to address corrections 4/18/2025 AMY GUEVARRA
Applicant returned to address corrections 4/22/2025 AMY GUEVARRA
Plan Check Approved 4/24/2025 AMY GUEVARRA
Issued 5/8/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/13/2025 DARIN LAM
Roof/Waste drainage to street Cleared 3/13/2025 DARIN LAM
Sewer availability Cleared 3/13/2025 DARIN LAM
GPI Written Notices Cleared 4/16/2025 AMY GUEVARRA
Grading Pre-Inspection Cleared 4/16/2025 AMY GUEVARRA

Contact Information

Contractor Rbc Construction; Lic. No.: 1001190-B 3141 TIGER RUN COURT STE 106      CARLSBAD, CA 92010

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 6/26/2026   

Inspection Request History

Pre-Inspection 5/15/2025 Partial Inspection JESUS PINEDA
Footing/Foundation/Slab 10/23/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/17/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 1/9/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 1/13/2026 Partial Approval HERBERT GIRON
PLUMBING-Rough 1/13/2026 Partial Approval HERBERT GIRON
Insulation 1/16/2026 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2026 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 3/3/2026 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued ANTHONY EGSON
Deputy Wood Construction 6/22/2026 Conditional Approval ANDREW NAVE
HVAC-Rough 6/24/2026 Corrections Issued EUGENE CASSIDY