317-319 W 78TH ST 90003
Certificate Information: 317-319 W 78TH ST 90003
- Application / Permit
- 25014-30000-00424
- Plan Check / Job No.
- B25WL00675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Supplemental permit to # 23014-30000-02082 to recheck per current code: Convert (E) garage to an ADU and 2nd story addition per LAMC 12.22 A.33(c) and (e). ***SEE COMMENTS***
- Permit Issued
- Issued on 2/7/2025
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 9/19/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2025 | DAVID CASTILLO |
| Corrections Issued | 1/31/2025 | DAVID CASTILLO |
| Plan Check Approved | 2/6/2025 | RICHARD GARCIA |
| Issued | 2/7/2025 | APPLICANT |
| Permit Finaled | 9/19/2025 | MICHAEL LEWIS |
Permit Application Clearance Information
| Address approval | Cleared | 2/5/2025 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2025 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 2/5/2025 | DAVID VO |
| Sewer availability | Cleared | 2/5/2025 | DAVID VO |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2025 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 2/21/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 2/24/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Approved | JOHN QUINTANILLA |
| Deputy Wood Construction | 3/26/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 4/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/11/2025 | Partial Approval | JOHN QUINTANILLA |
| HVAC-Rough | 4/11/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/11/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/16/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Rough | 4/16/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 4/16/2025 | Partial Inspection | JOHN QUINTANILLA |
| MERV13>=Rough | 4/16/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/16/2025 | Partial Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/28/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 4/30/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 5/2/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 5/6/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 7/21/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Final | 7/25/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 7/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| MERV13>=Final | 7/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 7/25/2025 | SGSOV Not Ready | LUIS CASTRO |
| Smoke Detectors | 7/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 7/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| Green Building Final | 7/29/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| MERV13>=Final | 7/29/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 7/29/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 8/1/2025 | Approved | LUIS CASTRO |
| Final | 8/1/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 8/1/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Final | 8/1/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 8/1/2025 | Approved | LUIS CASTRO |
| Final | 8/14/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 8/14/2025 | Approved | JOHN QUINTANILLA |
| Final | 8/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Sewer | 8/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/2/2025 | Corrections Issued | JOHN QUINTANILLA |
| Sewer | 9/3/2025 | Approved | JOHN QUINTANILLA |
| Final | 9/10/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 9/19/2025 | Corrections Issued | JEFFREY MEAD |