3049 S EARLMAR DR 90064
Certificate Information: 3049 S EARLMAR DR 90064
- Application / Permit
- 25014-30000-00350
- Plan Check / Job No.
- B25WL00496
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR RENOVATION AND 499 SF ADDITION TO A ONE STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 4/23/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | KAVIAN REFAHI |
| Corrections Issued | 2/3/2025 | KAVIAN REFAHI |
| Quality Review Completed | 2/10/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/13/2025 | APPLICANT |
| Applicant returned to address corrections | 4/17/2025 | KAVIAN REFAHI |
| Plan Check Approved | 4/21/2025 | KAVIAN REFAHI |
| Issued | 4/23/2025 | APPLICANT |
| CofO in Progress | 2/3/2026 | ASHLEY THOMPSON |
| Permit Finaled | 2/4/2026 | RICHARD STEINBACH |
| CofO Issued | 2/4/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/4/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/22/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/24/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/25/2025 | JOSHUA JONES |
| GPI Written Notices | Cleared | 4/17/2025 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 4/17/2025 | KAVIAN REFAHI |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Guideline Builders Inc; Lic. No.: 1021305-B | 2110 ARTESIA BLVD 886 REDONDO BEACH, CA 90278 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/15/2025 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 5/19/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 5/19/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 5/19/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/22/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 6/27/2025 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 7/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 7/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/8/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/10/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 7/10/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/14/2025 | Approved | EVAN COOPER |
| Green Building Rough | 7/14/2025 | Approved | EVAN COOPER |
| Shower Pan | 7/14/2025 | Approved | EVAN COOPER |
| Wood Frame | 7/14/2025 | Approved | EVAN COOPER |
| Insulation | 7/16/2025 | Corrections Issued | JEFFREY MEAD |
| Drywall Nailing | 7/25/2025 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 7/25/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 7/29/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/12/2025 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 8/12/2025 | Partial Inspection | JAYLIN GRAVITTE |
| ELECTRICAL-Final | 1/22/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 1/22/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/22/2026 | Approved | ASHLEY THOMPSON |
| Final | 1/27/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 1/27/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 1/27/2026 | Approved | ASHLEY THOMPSON |
| Final | 2/2/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/2/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Service/Power Release | 2/2/2026 | Approved | ASHLEY THOMPSON |