4619 W 6TH ST 90020
Certificate Information: 4619 W 6TH ST 90020
- Application / Permit
- 25014-30000-00191
- Plan Check / Job No.
- B25WL00241
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 316 SF to (E) 2nd floor. Add over (E) 1st fl. Add 60SF at 1st Floor.Per ZA-2024-5200-ADJ-COA
- Permit Issued
- Issued on 5/2/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | ALFREDO JARA |
| Corrections Issued | 1/18/2025 | ALFREDO JARA |
| Building Plans Picked Up | 1/23/2025 | APPLICANT |
| Applicant returned to address corrections | 3/7/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 3/7/2025 | JOHNPAUL ISIP |
| Issued | 5/2/2025 | APPLICANT |
| CofO in Progress | 5/8/2026 | RONNIE MINDANAO |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| CofO Issued | 5/8/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/19/2025 | EDGAR PASCUA |
| Roof/Waste drainage to street | Cleared | 2/22/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2025 | JESSICA OPINION |
| HPOZ | Cleared | 3/5/2025 | GEORGIA SMITH |
| Miscellaneous | Cleared | 3/5/2025 | GEORGIA SMITH |
| ZA Case | Cleared | 3/5/2025 | GEORGIA SMITH |
| ZA Case | Cleared | 3/5/2025 | GEORGIA SMITH |
Contact Information
| Architect | Kimball,, Dara; Lic. No.: C20715 | 2118 WILSHIRE BLVD 714 SANTA MONICA, CA 90403 |
| Contractor | R G Renovations Inc; Lic. No.: 654729-B | 10517 DES MOINES AVENUE NORTHRIDGE, CA 91326 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2025 | Partial Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/19/2025 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 5/19/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 5/19/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 7/29/2025 | Corrections Issued | ANTHONY RAMOS |
| Sewer | 7/29/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Rough | 8/11/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 8/11/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | RONNIE MINDANAO |
| Deputy Wood Construction | 10/1/2025 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/2/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 10/2/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 10/2/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 10/3/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 10/3/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/6/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 10/9/2025 | Approved | RONNIE MINDANAO |
| Insulation | 10/10/2025 | Conditional Approval | RONNIE MINDANAO |
| Drywall Nailing | 10/17/2025 | Approved | JOSH MEISTER |
| Insulation | 10/17/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 11/25/2025 | Approved | RONNIE MINDANAO |
| Service/Power Release | 11/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 11/25/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 3/24/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Gas Test | 3/24/2026 | Approved | RONNIE MINDANAO |
| HVAC-Final | 3/24/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 3/24/2026 | Approved | RONNIE MINDANAO |
| Service/Power Release | 3/24/2026 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 4/1/2026 | Approved | RAUL BARAJAS |
| Final | 4/1/2026 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 4/1/2026 | Approved | RAUL BARAJAS |
| Green Building Rough | 4/1/2026 | Approved | RAUL BARAJAS |
| HVAC-Final | 4/1/2026 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 4/1/2026 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 4/1/2026 | Approved | RAUL BARAJAS |
| Smoke Detectors | 4/1/2026 | Approved | RAUL BARAJAS |
| Final | 4/7/2026 | Corrections Issued | RONNIE MINDANAO |
| Final | 4/10/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 4/27/2026 | Partial Approval | RONNIE MINDANAO |
| Deputy Reinf. Concrete | 5/5/2026 | Conditional Approval | RONNIE MINDANAO |
| Final | 5/6/2026 | OK to Issue CofO | RONNIE MINDANAO |