ePlan: Supplemental to remove pool bath and exterior laundry room from scope of work.
Permit Issued
Issued on 1/21/2026
Issuing Office
Current Status
Issued on 1/21/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/19/2026 APPLICANT
Assigned to Plan Check Engineer 1/20/2026 AMY GUEVARRA
Plan Check Approved 1/21/2026 AMY GUEVARRA
Issued 1/21/2026 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/24/2026   

Inspection Request History

BUILDING-Rough-Frame 2/18/2026 Partial Inspection MICHEL ABAJAN
Drywall Nailing 2/18/2026 Partial Inspection MICHEL ABAJAN
Pre-Inspection 2/18/2026 Partial Inspection MICHEL ABAJAN
Pre-Inspection 2/23/2026 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 3/16/2026 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/20/2026 Approved MICHEL ABAJAN
Sewer 3/26/2026 Approved MICHEL ABAJAN
Sewer 4/2/2026 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/20/2026 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/20/2026 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/20/2026 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/22/2026 Approved MISAEL ESPARZA
HVAC-Rough 4/22/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/22/2026 Approved MISAEL ESPARZA
HVAC-Rough 4/28/2026 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/28/2026 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/28/2026 Approved MISAEL ESPARZA
Wood Frame 4/30/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/1/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/1/2026 Approved VINCENT HANLEY
Green Building Rough 5/1/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/1/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/4/2026 Approved MICHEL ABAJAN
Drywall Nailing 5/12/2026 Approved MICHEL ABAJAN