6245 N LANGDON AVE 91411
Certificate Information: 6245 N LANGDON AVE 91411
- Application / Permit
- 25014-20000-05676
- Plan Check / Job No.
- B25VN31171
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT 17'-10" X 20' DETACHED GARAGE AND ADD 19'-11.5" X 32'-6" 2-STORY FOR (N) ACCESORY DWELLING UNIT PER LAMC12.22A.33(b)(1). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/25/2026
- Issuing Office
- Current Status
- Issued on 6/25/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/4/2025 | APPLICANT |
| Assigned to Zoning Architect | 12/11/2025 | SAAD LADHANI |
| Assigned to Plan Check Engineer | 12/18/2025 | RAPHAEL ROSAS |
| Corrections Issued | 12/24/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 12/26/2025 | STEVEN KIM |
| Applicant returned to address corrections | 2/2/2026 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/16/2026 | RAPHAEL ROSAS |
| Plan Check Approved | 4/17/2026 | RAPHAEL ROSAS |
| Plan Check Approved | 6/25/2026 | RAPHAEL ROSAS |
| Issued | 6/25/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2026 | JEFF LOREDO |
| Roof/Waste drainage to street | Cleared | 1/30/2026 | JEFF LOREDO |
| Zoning Plan Check | Cleared | 3/2/2026 | SAAD LADHANI |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2026 | DERRICK MAGEE |
| Sewer availability | Cleared | 3/31/2026 | DERRICK MAGEE |
| Construction near power lines | Cleared | 4/16/2026 | AARON DIZON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/14/2026 | Partial Approval | KEVIN BERBERYAN |
| Sewer | 7/14/2026 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 7/17/2026 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/17/2026 | Approved | VINCENT HANLEY |