18544 W SUNBURST ST 91324

Certificate Information: 18544 W SUNBURST ST 91324

Application / Permit
25014-20000-05640
Plan Check / Job No.
B25VN37306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE PORTION OF (E) DET GARAGE, CONVERT REMAINING DET GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1), ALL WORK PER WFPP.
Permit Issued
Issued on 4/30/2026
Issuing Office
Valley
Current Status
Issued on 4/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2025 APPLICANT
Assigned to Plan Check Engineer 12/31/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/1/2026 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 1/7/2026 APPLICANT
Applicant returned to address corrections 4/22/2026 LUISANGEL VALENZUELA
Plan Check Approved 4/29/2026 ISIS ARGUETA
Issued 4/30/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/30/2026 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/30/2026 LEE GUILBEAUX
Sewer availability Cleared 1/30/2026 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/30/2026 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/3/2026 LEE GUILBEAUX
Construction near power lines Cleared 3/11/2026 GEVORK KARAPETYAN
Construction within easement Cleared 3/11/2026 GEVORK KARAPETYAN

Contact Information

Contractor Ea Constructions Inc; Lic. No.: 1096892-B 8937 HASKELL AVE      NORTH HILLS, CA 91343

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2026 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 5/15/2026 Approved JEFFREY PARD
Sewer 5/15/2026 Approved JEFFREY PARD
Sewer 5/15/2026 Partial Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/19/2026 Approved JACK KARGODORIAN
Footing/Foundation/Slab 5/19/2026 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/12/2026 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 6/12/2026 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/12/2026 Approved JACK KARGODORIAN
Gas Test 6/12/2026 Corrections Issued JACK KARGODORIAN
Green Building Rough 6/12/2026 Approved JACK KARGODORIAN
HVAC-Rough 6/12/2026 Approved JACK KARGODORIAN
PLUMBING-Rough 6/12/2026 Partial Approval JACK KARGODORIAN
Wood Frame 6/12/2026 Not Ready for Inspection JACK KARGODORIAN