8303-8305 N DUCOR AVE 91304

Certificate Information: 8303-8305 N DUCOR AVE 91304

Application / Permit
25014-20000-05565
Plan Check / Job No.
B25VN36797
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ACCESSORY DWELLING UNIT ADDITION TO REAR OF (E) SFD PER LAMC 12.22 A.33(c) and (e). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/24/2026
Issuing Office
Current Status
Issued on 2/24/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2025 APPLICANT
Assigned to Plan Check Engineer 12/24/2025 GURUNATH NESARAJAH
Corrections Issued 12/24/2025 GURUNATH NESARAJAH
Plan Check Approved 2/23/2026 GURUNATH NESARAJAH
Issued 2/24/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/6/2026 ROSE STEIN-WENDT
Eng Process Fee Ord 176,300 Cleared 1/14/2026 ROSE STEIN-WENDT
Sewer availability Cleared 1/14/2026 ROSE STEIN-WENDT
Grading Pre-Inspection Cleared 2/6/2026 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 2/10/2026 ROSE STEIN-WENDT

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: NA54382       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/19/2026 Partial Approval CHRIS CHRISTENSEN
Sewer 3/19/2026 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 3/24/2026 Conditional Approval JEFFREY HARTLINE
Footing/Foundation/Slab 3/24/2026 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/23/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/12/2026 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/12/2026 Not Ready for Inspection CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/12/2026 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/28/2026 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/28/2026 Approved CHRIS CHRISTENSEN
Insulation 5/28/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/28/2026 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 5/28/2026 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/4/2026 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/4/2026 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/4/2026 Partial Approval CHRIS CHRISTENSEN
Shower Pan 6/4/2026 Approved CHRIS CHRISTENSEN