6670-6672 N PLATT AVE 91307
Certificate Information: 6670-6672 N PLATT AVE 91307
- Application / Permit
- 25014-20000-05453
- Plan Check / Job No.
- B25VN36056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Remodel and addition to (e) 1-story SFD with attached garage conversion to ADU per GC 66323(a)(1). NFPA13D sprinkler is required.
- Permit Issued
- Issued on 1/14/2026
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2025 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/18/2025 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 1/9/2026 | KAVIAN REFAHI |
| Plan Check Approved | 1/13/2026 | KAVIAN REFAHI |
| Issued | 1/14/2026 | APPLICANT |
| CofO in Progress | 4/16/2026 | TROY SANDERS |
| Permit Finaled | 4/30/2026 | JOHN JANSON |
| CofO Issued | 4/30/2026 | JOHN JANSON |
| Permit Finaled | 4/30/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 12/22/2025 | ABEL CASILLAS |
| ZA Case | Cleared | 12/22/2025 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2026 | JEREMY CHOK |
| Sewer availability | Cleared | 1/2/2026 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gourehzar,, Tedis; Lic. No.: C98604 | 513 W WILSON AVE GLENDALE, CA 91203 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/16/2026 | Partial Approval | TROY SANDERS |
| Sewer | 1/16/2026 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 1/20/2026 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 1/20/2026 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 2/4/2026 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 2/10/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 2/10/2026 | Approved | TROY SANDERS |
| Green Building Rough | 2/10/2026 | Approved | TROY SANDERS |
| HVAC-Rough | 2/10/2026 | Approved | TROY SANDERS |
| PLUMBING-Rough | 2/10/2026 | Approved | TROY SANDERS |
| Shower Pan | 2/10/2026 | Approved | TROY SANDERS |
| Insulation | 2/18/2026 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/18/2026 | Approved | TROY SANDERS |
| Drywall Nailing | 2/23/2026 | Approved | ARUTYUN MADATYAN |
| Pre-Inspection | 3/27/2026 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 4/9/2026 | Approved | TROY SANDERS |
| Final | 4/9/2026 | Corrections Issued | TROY SANDERS |
| Green Building Final | 4/9/2026 | Approved | TROY SANDERS |
| HVAC-Final | 4/9/2026 | Approved | TROY SANDERS |
| PLUMBING-Final | 4/9/2026 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/9/2026 | Approved | TROY SANDERS |
| Final | 4/13/2026 | Not Ready for Inspection | TROY SANDERS |
| Final | 4/16/2026 | OK to Issue CofO | TROY SANDERS |