7931 N LASAINE AVE 91325

Certificate Information: 7931 N LASAINE AVE 91325

Application / Permit
25014-20000-05425
Plan Check / Job No.
B25VN35913
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition to (E) Single Family Dwelling w/ attached garage in the front. Convert (E) Patio Covers in the front and rear to be part of (E) SFD.
Permit Issued
Issued on 12/29/2025
Issuing Office
Current Status
Issued on 12/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/10/2025 APPLICANT
Assigned to Plan Check Engineer 12/15/2025 AMY GUEVARRA
Corrections Issued 12/15/2025 AMY GUEVARRA
Applicant returned to address corrections 12/26/2025 AMY GUEVARRA
Plan Check Approved 12/28/2025 AMY GUEVARRA
Issued 12/29/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/24/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 12/24/2025 DERRICK MAGEE
Sewer availability Cleared 12/24/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George H; Lic. No.: NA64144       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/26/2026 Partial Approval GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 2/2/2026 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 2/2/2026 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 2/4/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/26/2026 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval JACK KARGODORIAN
Green Building Rough 2/26/2026 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 3/10/2026 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/10/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 3/10/2026 Corrections Issued GAREN HAYRAPETYAN
Deputy Wood Construction 3/12/2026 Conditional Approval JOSE AVILA
PLUMBING-Rough 3/17/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/23/2026 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Approved KIRK SANDERS
Green Building Rough 3/23/2026 Corrections Issued KIRK SANDERS
Wood Frame 3/23/2026 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 4/6/2026 Approved KIRK SANDERS
Green Building Rough 4/6/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 4/6/2026 Partial Approval KIRK SANDERS
Insulation 4/10/2026 Approved JOSE AVILA
Drywall Nailing 4/20/2026 Approved DAVID MATSON
Shower Pan 4/20/2026 Approved DAVID MATSON
Deputy Wood Construction 5/4/2026 Conditional Approval KIRK SANDERS
Insulation 5/8/2026 Approved KIRK SANDERS