23314 W GONZALES DR 91367

Certificate Information: 23314 W GONZALES DR 91367

Application / Permit
25014-20000-05373
Plan Check / Job No.
B25VN35560
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. PROPOSED ADDITION AND REMODEL TO THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/9/2026
Issuing Office
Current Status
Issued on 1/9/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/8/2025 APPLICANT
Assigned to Plan Check Engineer 12/11/2025 SARKIS HARABEDIAN
Corrections Issued 12/12/2025 SARKIS HARABEDIAN
Plan Check Approved 12/18/2025 SARKIS HARABEDIAN
Issued 1/9/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/16/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 12/16/2025 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 12/16/2025 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/26/2026 Conditional Approval GEVORK IPCHYAN
Footing/Foundation/Slab 1/27/2026 Approved GEVORK IPCHYAN
ELECTRICAL-Rough 2/9/2026 Not Ready for Inspection GEVORK IPCHYAN
Gas Test 2/9/2026 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Rough 2/9/2026 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 2/9/2026 Partial Approval GEVORK IPCHYAN
Wood Frame 2/9/2026 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 2/11/2026 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 2/13/2026 Approved GEVORK IPCHYAN
Gas Test 2/13/2026 Approved GEVORK IPCHYAN
HVAC-Rough 2/13/2026 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 2/13/2026 Approved GEVORK IPCHYAN
Wood Frame 2/13/2026 Partial Approval GEVORK IPCHYAN
BUILDING-Rough-Frame 2/19/2026 Partial Approval GEVORK IPCHYAN
Green Building Rough 2/19/2026 Approved GEVORK IPCHYAN
Insulation 2/19/2026 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 2/19/2026 Partial Approval GEVORK IPCHYAN
METHANE-Rough 2/19/2026 Approved GEVORK IPCHYAN
Drywall Nailing 2/23/2026 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 2/27/2026 Approved DAVID FASTIGGI
Interior/Exterior Lathing 3/3/2026 Approved DAVID FASTIGGI
Shower Pan 3/3/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 7/22/2026 No Result Entered TROY SANDERS
ELECTRICAL-Final 7/22/2026 No Result Entered TROY SANDERS
Final 7/22/2026 No Result Entered TROY SANDERS
MERV13>=Final 7/22/2026 No Result Entered TROY SANDERS
MERV13>=Rough 7/22/2026 No Result Entered TROY SANDERS
PLUMBING-Final 7/22/2026 No Result Entered TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/22/2026 No Result Entered TROY SANDERS
Smoke Detectors 7/22/2026 No Result Entered TROY SANDERS