7115 N MATILIJA AVE 91405
Certificate Information: 7115 N MATILIJA AVE 91405
- Application / Permit
- 25014-20000-05309
- Plan Check / Job No.
- B25VN35093
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATTACHED PATIO COVER AND ADD IRREG SHAPED ADDITION AND REMODEL TO RELOCATE KITCHEN, BEDROOM, AND BATHROOM IN REAR, ADDITION TO ENLARGE LIVING ROOM IN FRONT. WORK PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 12/29/2025
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 12/9/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/10/2025 | APPLICANT |
| Plan Check Approved | 12/29/2025 | OMAR GARNICA |
| Issued | 12/29/2025 | APPLICANT |
| CofO in Progress | 5/15/2026 | VINCENT HANLEY |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/11/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/20/2026 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 1/21/2026 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/21/2026 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/5/2026 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/5/2026 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/20/2026 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/20/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/20/2026 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/25/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/25/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | VINCENT HANLEY |
| Insulation | 3/5/2026 | Approved | VINCENT HANLEY |
| Shower Pan | 3/5/2026 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/10/2026 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/10/2026 | Approved | VINCENT HANLEY |
| Final | 5/6/2026 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/6/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/6/2026 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/12/2026 | Approved | VINCENT HANLEY |
| Final | 5/12/2026 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 5/12/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/12/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 5/12/2026 | Approved | VINCENT HANLEY |
| Final | 5/15/2026 | OK to Issue CofO | VINCENT HANLEY |