7115 N MATILIJA AVE 91405

Certificate Information: 7115 N MATILIJA AVE 91405

Application / Permit
25014-20000-05309
Plan Check / Job No.
B25VN35093
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) ATTACHED PATIO COVER AND ADD IRREG SHAPED ADDITION AND REMODEL TO RELOCATE KITCHEN, BEDROOM, AND BATHROOM IN REAR, ADDITION TO ENLARGE LIVING ROOM IN FRONT. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 12/29/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2025 APPLICANT
Assigned to Plan Check Engineer 12/5/2025 JEROME MAGAT PALMA
Corrections Issued 12/9/2025 JEROME MAGAT PALMA
Building Plans Picked Up 12/10/2025 APPLICANT
Plan Check Approved 12/29/2025 OMAR GARNICA
Issued 12/29/2025 APPLICANT
CofO in Progress 5/15/2026 VINCENT HANLEY
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/11/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 12/17/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2026 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 1/21/2026 Approved RYAN SALAZAR
Footing/Foundation/Slab 1/21/2026 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Partial Approval JACK KARGODORIAN
Insulation 2/5/2026 Partial Approval VINCENT HANLEY
PLUMBING-Rough 2/5/2026 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/20/2026 Approved VINCENT HANLEY
HVAC-Rough 2/20/2026 Approved VINCENT HANLEY
PLUMBING-Rough 2/20/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/25/2026 Approved VINCENT HANLEY
Green Building Rough 2/25/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/2/2026 Partial Approval VINCENT HANLEY
Insulation 3/5/2026 Approved VINCENT HANLEY
Shower Pan 3/5/2026 Approved VINCENT HANLEY
Drywall Nailing 3/10/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/10/2026 Approved VINCENT HANLEY
Final 5/6/2026 Corrections Issued MATTHEW NELSON
Green Building Final 5/6/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 5/6/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 5/12/2026 Approved VINCENT HANLEY
Final 5/12/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 5/12/2026 Approved VINCENT HANLEY
PLUMBING-Final 5/12/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/12/2026 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/12/2026 Approved VINCENT HANLEY
Final 5/15/2026 OK to Issue CofO VINCENT HANLEY