11215-11217 W LULL ST 91352

Certificate Information: 11215-11217 W LULL ST 91352

Application / Permit
25014-20000-05105
Plan Check / Job No.
B25VN33738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition and conversion of (e) attached garage to JADU per GC 66323(a)(1) and 66333
Permit Issued
Issued on 1/26/2026
Issuing Office
Current Status
CofO in Progress on 6/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/17/2025 APPLICANT
Assigned to Plan Check Engineer 11/20/2025 REZA HAGHIGHAT
Corrections Issued 11/21/2025 REZA HAGHIGHAT
Applicant returned to address corrections 1/9/2026 REZA HAGHIGHAT
Plan Check Approved 1/21/2026 REZA HAGHIGHAT
Issued 1/26/2026 APPLICANT
CofO in Progress 6/30/2026 MATTHEW NELSON

Permit Application Clearance Information

Address approval Cleared 12/15/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 12/18/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 12/18/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 1/8/2026 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazarian,, Varoojan; Lic. No.: NA94135       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2026 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/5/2026 Approved MATTHEW NELSON
Footing/Foundation/Slab 3/5/2026 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Not Ready for Inspection MATTHEW NELSON
Deputy Wood Construction 3/26/2026 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/7/2026 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 4/7/2026 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/7/2026 Partial Approval MATTHEW NELSON
Green Building Rough 4/7/2026 Approved MATTHEW NELSON
PLUMBING-Rough 4/7/2026 Corrections Issued MATTHEW NELSON
Wood Frame 4/7/2026 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/15/2026 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 4/15/2026 Corrections Issued DAVID MATSON
Wood Frame 4/15/2026 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 4/27/2026 Approved MATTHEW NELSON
PLUMBING-Rough 4/27/2026 Approved MATTHEW NELSON
Insulation 5/5/2026 Approved MATTHEW NELSON
Drywall Nailing 5/8/2026 Approved MATTHEW NELSON
Gas Test 5/8/2026 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 5/8/2026 Partial Approval MATTHEW NELSON
Shower Pan 6/2/2026 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/4/2026 Approved MATTHEW NELSON
Wood Frame 6/4/2026 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 6/24/2026 Corrections Issued MATTHEW NELSON
Final 6/24/2026 Corrections Issued MATTHEW NELSON
Green Building Final 6/24/2026 Corrections Issued MATTHEW NELSON
PLUMBING-Final 6/24/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/24/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 6/24/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 6/29/2026 Approved MATTHEW NELSON
Final 6/29/2026 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/29/2026 Approved MATTHEW NELSON