9955 N NORWICH AVE 91345
Certificate Information: 9955 N NORWICH AVE 91345
- Application / Permit
- 25014-20000-05096
- Plan Check / Job No.
- B25VN33698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k).
- Permit Issued
- Issued on 12/1/2025
- Issuing Office
- Current Status
- Issued on 12/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2025 | JESSE ARELLANO |
| Corrections Issued | 11/21/2025 | JESSE ARELLANO |
| Building Plans Picked Up | 11/24/2025 | APPLICANT |
| Plan Check Approved | 12/1/2025 | NAREG ATARIAN |
| Issued | 12/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2025 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 11/24/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/24/2025 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/1/2026 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/3/2026 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 4/6/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/14/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/14/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/23/2026 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/23/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 6/2/2026 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 6/2/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 6/2/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/2/2026 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/12/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/12/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/12/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/30/2026 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/30/2026 | Approved | JENNIFER RABUCHIN |