23463 W SYLVAN ST 91367

Certificate Information: 23463 W SYLVAN ST 91367

Application / Permit
25014-20000-04970
Plan Check / Job No.
B25VN32897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO NEW BEDRMS, HALLWAY &BATHRM ADDN AT FRONT. PROPOSED ADDN AT REAR TO ENLARGE EX LIVING & DINING RMS. NEW FRONT 'TOWER' PORCH (ENCLOSED 3 SIDES) ADDN. CONVERT EX BEDRM INTO BATHRM & CLOSET FOR EX ADJ BEDRM. REMODEL EX KITCHEN & BATHRMS. REMOVE & REPLACE ALL EXISTING WINDOWS & DOORS PER PLAN. <NFPA-13D FIRE SPRINKLER THRU-OUT>
Permit Issued
Issued on 11/24/2025
Issuing Office
Valley
Current Status
CofO in Progress on 5/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/7/2025 APPLICANT
Assigned to Plan Check Engineer 11/13/2025 HAYATO TSUCHIYA
Corrections Issued 11/13/2025 HAYATO TSUCHIYA
Building Plans Picked Up 11/14/2025 APPLICANT
Issued 11/24/2025 APPLICANT
CofO in Progress 5/14/2026 TROY SANDERS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/20/2025 JEREMY CHOK
Roof/Waste drainage to street Cleared 11/20/2025 JEREMY CHOK
Sewer availability Cleared 11/20/2025 JEREMY CHOK

Contact Information

Contractor Adu Builder And Construction Inc; Lic. No.: 1122843-B 5030 NEWCASTLE AVE      ENCINO, CA 91316
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/1/2025 Conditional Approval TROY SANDERS
PLUMBING-Rough 12/2/2025 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 12/4/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Partial Approval TROY SANDERS
Interior/Exterior Lathing 1/8/2026 Partial Approval TROY SANDERS
PLUMBING-Rough 1/8/2026 Approved TROY SANDERS
Shower Pan 1/8/2026 Approved TROY SANDERS
BUILDING-Rough-Frame 1/20/2026 Approved TROY SANDERS
ELECTRICAL-Rough 1/20/2026 Approved TROY SANDERS
Green Building Rough 1/20/2026 Approved TROY SANDERS
HVAC-Rough 1/20/2026 Approved TROY SANDERS
Insulation 1/21/2026 Approved TROY SANDERS
Drywall Nailing 1/26/2026 Approved TROY SANDERS
Final 4/28/2026 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 4/28/2026 Approved TROY SANDERS
Green Building Final 4/28/2026 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved TROY SANDERS
Smoke Detectors 4/28/2026 Approved TROY SANDERS
Final 5/12/2026 OK to Issue CofO TROY SANDERS