15741 W VALERIO ST 91406
Certificate Information: 15741 W VALERIO ST 91406
- Application / Permit
- 25014-20000-04949
- Plan Check / Job No.
- B25VN32709
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family residence per SB 9 (1027 SF) addition to existing garage, nfpa-13d Fire Sprinklers throughout, all work per engineering
- Permit Issued
- Issued on 2/9/2026
- Issuing Office
- Current Status
- Issued on 2/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/7/2025 | APPLICANT |
| Assigned to Zoning Architect | 11/20/2025 | ELAHE MERRIKHI |
| Assigned to Plan Check Engineer | 11/25/2025 | RARES BODEA |
| Corrections Issued | 12/1/2025 | RARES BODEA |
| Quality Review Completed | 12/3/2025 | STEVEN KIM |
| Applicant returned to address corrections | 1/29/2026 | RARES BODEA |
| Applicant returned to address corrections | 2/6/2026 | RARES BODEA |
| Plan Check Approved | 2/6/2026 | RARES BODEA |
| Issued | 2/9/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 12/23/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 1/5/2026 | MICHAEL BROWN |
| Senate Bill 9 | Cleared | 1/5/2026 | FIPE LEILUA |
| Construction within easement | Cleared | 1/8/2026 | GEVORK KARAPETYAN |
| Zoning Plan Check | Cleared | 1/21/2026 | ELAHE MERRIKHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 6/10/2026 |
| PLUMBING-Final | 6/10/2026 |
| HVAC-Final | 6/10/2026 |
Inspection Request History
| PLUMBING-Rough | 2/24/2026 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 2/25/2026 | Conditional Approval | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 3/3/2026 | Conditional Approval | KIRK SANDERS |
| Sewer | 3/11/2026 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 3/11/2026 | Partial Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/2/2026 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 4/9/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 4/9/2026 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/9/2026 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 4/10/2026 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/16/2026 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/16/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/16/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/16/2026 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/16/2026 | Approved | JENNIFER RABUCHIN |
| Sewer | 4/16/2026 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 4/16/2026 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 4/21/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/21/2026 | Partial Approval | MICHAEL CORTEZ |
| Shower Pan | 4/21/2026 | Corrections Issued | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 4/24/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/24/2026 | Approved | MATTHEW NELSON |
| Insulation | 4/24/2026 | Approved | MATTHEW NELSON |
| Shower Pan | 4/24/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/28/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 4/28/2026 | Approved | MICHAEL CORTEZ |