153 1/2-1/4 W 51ST ST 90037
Certificate Information: 153 1/2-1/4 W 51ST ST 90037
- Application / Permit
- 25014-20000-04885
- Plan Check / Job No.
- B25VN32216
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Addition and Conversion of the (E) Detached Garage to (2) New Detached ADUs per GC 66323(a)(4).
- Permit Issued
- Issued on 2/13/2026
- Issuing Office
- Current Status
- Issued on 2/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | TSE MING HUANG |
| Corrections Issued | 11/7/2025 | TSE MING HUANG |
| Plan Check Approved | 12/3/2025 | TSE MING HUANG |
| Plan Check Approved | 2/12/2026 | TSE MING HUANG |
| Issued | 2/13/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/17/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/17/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/17/2026 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/21/2026 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 5/28/2026 | Conditional Approval | ALEX COLIN |
| ELECTRICAL-Rough | 6/10/2026 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 6/10/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 6/10/2026 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/12/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/12/2026 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/15/2026 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/15/2026 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 6/15/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 6/15/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/18/2026 | Corrections Issued | ALEX COLIN |
| Insulation | 6/18/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 6/18/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 6/22/2026 | Approved | BARRY HACHE |
| Sewer | 7/14/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 7/15/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |