13365-13367 W GARBER ST 91331
Certificate Information: 13365-13367 W GARBER ST 91331
- Application / Permit
- 25014-20000-04878
- Plan Check / Job No.
- B25VN32198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADD TO AND CONVERT PORTION OF (E) SFD TO SB9 TO CREATE A DUPLEX , ALL WORK ENGINEERING
- Permit Issued
- Issued on 1/27/2026
- Issuing Office
- Current Status
- CofO in Progress on 6/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | RARES BODEA |
| Assigned to Zoning Architect | 11/6/2025 | MEGAN KOLP |
| Corrections Issued | 11/10/2025 | RARES BODEA |
| Quality Review Completed | 11/12/2025 | STEVEN KIM |
| Building Plans Picked Up | 11/12/2025 | APPLICANT |
| Plan Check Approved | 1/27/2026 | RARES BODEA |
| Issued | 1/27/2026 | APPLICANT |
| CofO in Progress | 6/23/2026 | MICHEL ABAJAN |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 11/14/2025 | JASON CHAN |
| Address approval | Cleared | 11/26/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/26/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/26/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/26/2025 | LEE GUILBEAUX |
| Zoning Plan Check | Cleared | 1/21/2026 | MEGAN KOLP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/30/2026 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/30/2026 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/30/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/30/2026 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 1/30/2026 | Partial Approval | MICHEL ABAJAN |
| METHANE-Rough | 1/30/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/30/2026 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 1/30/2026 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 1/30/2026 | Partial Inspection | MICHEL ABAJAN |
| Drywall Nailing | 2/5/2026 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/5/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/5/2026 | Partial Approval | MICHEL ABAJAN |
| Insulation | 2/5/2026 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/5/2026 | Partial Approval | MICHEL ABAJAN |
| Shower Pan | 2/5/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/10/2026 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/10/2026 | Partial Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/19/2026 | Approved | MICHEL ABAJAN |
| Shower Pan | 2/19/2026 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/24/2026 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/24/2026 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2026 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/24/2026 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/24/2026 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/24/2026 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/6/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/6/2026 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/6/2026 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/6/2026 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/6/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/6/2026 | Approved | MICHEL ABAJAN |
| Insulation | 3/10/2026 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/13/2026 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 5/28/2026 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/8/2026 | Approved | MICHEL ABAJAN |
| Final | 6/8/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/8/2026 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/8/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/8/2026 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 6/8/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/8/2026 | Approved | MICHEL ABAJAN |
| Final | 6/22/2026 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2026 | SGSOV Approved | MICHEL ABAJAN |