11538 W CUMPSTON ST 91601

Certificate Information: 11538 W CUMPSTON ST 91601

Application / Permit
25014-20000-04808
Plan Check / Job No.
B25VN31719
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT (E) DETACHED GARAGE INTO ADU AND ADDITION TO ADU. PER LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 11/22/2025
Issuing Office
Current Status
Issued on 11/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2025 APPLICANT
Assigned to Plan Check Engineer 11/6/2025 ALFREDO JARA
Corrections Issued 11/7/2025 ALFREDO JARA
Plan Check Approved 11/17/2025 ALFREDO JARA
Issued 11/22/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/10/2025 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 11/10/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/10/2025 LEE GUILBEAUX
Sewer availability Cleared 11/10/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/10/2025 LEE GUILBEAUX

Contact Information

Architect Sigala,, Wei; Lic. No.: NA41989       ,
Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2025 Partial Approval JAVIER RAMOS JR
Sewer 12/17/2025 Approved JAVIER RAMOS JR
Underground Mechanical 12/17/2025 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 12/23/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/31/2025 Approved JAVIER RAMOS JR
Deputy Wood Construction 1/23/2026 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 2/2/2026 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/2/2026 Approved JAVIER RAMOS JR
HVAC-Rough 2/2/2026 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/2/2026 Approved JAVIER RAMOS JR
Wood Frame 2/2/2026 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 2/12/2026 Approved JAVIER RAMOS JR
Green Building Rough 2/12/2026 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 2/12/2026 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 2/12/2026 Approved JAVIER RAMOS JR
Insulation 2/19/2026 Approved MICHAEL CORTEZ
Shower Pan 2/19/2026 Approved MICHAEL CORTEZ
Drywall Nailing 2/26/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/29/2026 Corrections Issued JAVIER RAMOS JR
Final 4/29/2026 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/29/2026 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 4/29/2026 Approved JAVIER RAMOS JR
MERV13>=Final 4/29/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 4/29/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/29/2026 Approved JAVIER RAMOS JR