20550 W WELLS DR 91364
Certificate Information: 20550 W WELLS DR 91364
- Application / Permit
- 25014-20000-04797
- Plan Check / Job No.
- B25VN31632
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND CONVERT PORTION OF ATTACHED GARAGE TO (E) SFD. FRONT ADDITION TO ENLARGE GARAGE.
- Permit Issued
- Issued on 11/25/2025
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 3/9/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/3/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 11/4/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/6/2025 | APPLICANT |
| Plan Check Approved | 11/25/2025 | SERGIO MUNIZ |
| Issued | 11/25/2025 | APPLICANT |
| CofO in Progress | 3/9/2026 | JOHN HAYES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 11/19/2025 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 11/25/2025 | MANUEL TEJADA |
Contact Information
| Contractor | Regal Construction & Remodeling Inc; Lic. No.: 909023-B | 19537 1/2 VENTURA BLVD TARZANA, CA 91356 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 12/5/2025 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/5/2025 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 12/5/2025 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/18/2025 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2025 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | SEAN WIRCH |
| Deputy Wood Construction | 1/21/2026 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 1/27/2026 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2026 | Approved | JOHN HAYES |
| Green Building Rough | 1/27/2026 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/27/2026 | Approved | JOHN HAYES |
| Insulation | 1/29/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/29/2026 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 2/2/2026 | Approved | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 2/17/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 2/17/2026 | Approved | JON MCHUGH |
| Final | 2/17/2026 | Corrections Issued | JON MCHUGH |
| Green Building Final | 2/17/2026 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 2/17/2026 | Approved | JON MCHUGH |
| HVAC-Final | 2/17/2026 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 2/17/2026 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 2/17/2026 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 3/4/2026 | Approved | JOHN HAYES |
| Final | 3/4/2026 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/4/2026 | Approved | JOHN HAYES |
| Final | 3/9/2026 | OK to Issue CofO | JOHN HAYES |