18417-18419 W ERWIN ST 91335
Certificate Information: 18417-18419 W ERWIN ST 91335
- Application / Permit
- 25014-20000-04789
- Plan Check / Job No.
- B25VN31598
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* Remodel and addition to (E) single family dwelling with attached garage conversion into an accessory dwelling unit per GC 66323(a)(1)
- Permit Issued
- Issued on 1/28/2026
- Issuing Office
- Current Status
- Issued on 1/28/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2025 | APPLICANT |
| Assigned to Zoning Architect | 11/6/2025 | KAITA SAITO |
| Assigned to Plan Check Engineer | 11/13/2025 | ALEXIS VERDUGO |
| Corrections Issued | 11/24/2025 | ALEXIS VERDUGO |
| Quality Review Completed | 11/25/2025 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/7/2026 | ALEXIS VERDUGO |
| Applicant returned to address corrections | 1/15/2026 | ALEXIS VERDUGO |
| Applicant returned to address corrections | 1/20/2026 | ALEXIS VERDUGO |
| Plan Check Approved | 1/27/2026 | ALEXIS VERDUGO |
| Issued | 1/28/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/10/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2025 | TONY CHIANG |
| Sewer availability | Cleared | 12/18/2025 | TONY CHIANG |
| Supp. Use District POD/CDO/TDO | Cleared | 12/19/2025 | ALEX VELA |
| Zoning Plan Check | Cleared | 12/23/2025 | Edwin Martinez |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/16/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Pre-Inspection | 4/16/2026 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 4/16/2026 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 4/20/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 4/23/2026 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/29/2026 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 4/29/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/30/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Rough | 4/30/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/1/2026 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/10/2026 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 6/15/2026 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2026 | Not Ready for Inspection | SEAN WIRCH |
| Gas Test | 6/16/2026 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 6/16/2026 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 6/18/2026 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2026 | Partial Approval | ARUTYUN MADATYAN |