9953 N NORWICH AVE 91345

Certificate Information: 9953 N NORWICH AVE 91345

Application / Permit
25014-20000-04737
Plan Check / Job No.
B25VN31328
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, ENCLOSE FRONT PORCH (47 SF), NEW SFD ADDITIONS (89 SF, 130 SF) AND PATIO COVER/PORCH ADDITIONS (493 SF, 93 SF)
Permit Issued
Issued on 12/1/2025
Issuing Office
Current Status
Issued on 12/1/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/23/2025 APPLICANT
Assigned to Plan Check Engineer 10/31/2025 ARTIN ZARUKIAN
Corrections Issued 11/1/2025 ARTIN ZARUKIAN
Building Plans Picked Up 11/3/2025 APPLICANT
Plan Check Approved 12/1/2025 ISIS ARGUETA
Issued 12/1/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/3/2025 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 11/3/2025 LEE GUILBEAUX
Sewer availability Cleared 11/3/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 11/3/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/17/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 12/19/2025 Partial Approval JOAQUIN GREENOUGH
Special/Order Compliance 12/19/2025 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/30/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 12/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/30/2025 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Partial Approval JENNIFER RABUCHIN
Green Building Rough 1/7/2026 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 1/7/2026 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 1/23/2026 No Result Entered JOHN COLEMAN
BUILDING-Rough-Frame 1/27/2026 Approved JENNIFER RABUCHIN
Green Building Rough 1/27/2026 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/11/2026 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/11/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/11/2026 Approved JENNIFER RABUCHIN
HVAC-Rough 2/11/2026 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 2/11/2026 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/11/2026 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 2/17/2026 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 2/18/2026 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 2/18/2026 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/18/2026 Approved JENNIFER RABUCHIN
Insulation 2/20/2026 Approved JENNIFER RABUCHIN
Drywall Nailing 2/26/2026 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/19/2026 Approved JENNIFER RABUCHIN
Shower Pan 3/19/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/22/2026 Approved JENNIFER RABUCHIN
Final 6/22/2026 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 6/22/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/22/2026 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 6/22/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/7/2026 Approved JENNIFER RABUCHIN
Final 7/7/2026 Partial Approval JENNIFER RABUCHIN
Green Building Final 7/7/2026 Approved JENNIFER RABUCHIN
HVAC-Final 7/7/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/7/2026 Approved JENNIFER RABUCHIN