5313 N CREBS AVE 91356
Certificate Information: 5313 N CREBS AVE 91356
- Application / Permit
- 25014-20000-04634
- Plan Check / Job No.
- B25VN30472
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL TO (E) SFD W/ IRR.-SHAPE ADDITION. ALL WORK DONE PER ENGNIEERING
- Permit Issued
- Issued on 12/2/2025
- Issuing Office
- Current Status
- Issued on 12/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2025 | ARTIN ZARUKIAN |
| Corrections Issued | 10/25/2025 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/29/2025 | APPLICANT |
| Plan Check Approved | 11/25/2025 | GURUNATH NESARAJAH |
| No Progress | 11/25/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/2/2025 | GURUNATH NESARAJAH |
| Issued | 12/2/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/26/2025 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 10/26/2025 | ARTIN ZARUKIAN |
| Sewer availability | Cleared | 11/7/2025 | BIAINA HARITUNIAN |
| Watercourse | Cleared | 11/7/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 11/10/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/9/2025 | Approved | JOHN KIDWELL |
| Shower Pan | 12/9/2025 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/12/2025 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/12/2025 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/15/2025 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 12/16/2025 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 12/16/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2026 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 1/5/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/9/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Wood Construction | 1/9/2026 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/9/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 1/9/2026 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 1/9/2026 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 1/9/2026 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/13/2026 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 1/13/2026 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 1/13/2026 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 1/13/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/13/2026 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/21/2026 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/21/2026 | Approved | JOHN KIDWELL |
| Insulation | 1/21/2026 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/21/2026 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 1/27/2026 | Approved | JOHN KIDWELL |