152 S ALMONT DR 90048
Certificate Information: 152 S ALMONT DR 90048
- Application / Permit
- 25014-20000-04622
- Plan Check / Job No.
- B25VN30417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 21'-5" X 31'-7" IRREGULAR SHAPED 2ND FLOOR ADDITION AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/18/2026
- Issuing Office
- Current Status
- Issued on 2/18/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 10/23/2025 | LINGHUI YU |
| Corrections Issued | 10/27/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 11/4/2025 | STEVEN KIM |
| Building Plans Picked Up | 11/5/2025 | APPLICANT |
| Applicant returned to address corrections | 12/17/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/2/2026 | RAPHAEL ROSAS |
| Plan Check Approved | 2/17/2026 | RAPHAEL ROSAS |
| Issued | 2/18/2026 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 11/18/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 11/18/2025 | JEREMY CHOK |
| Zoning Plan Check | Cleared | 12/1/2025 | LINGHUI YU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nirattisai,, Preston; Lic. No.: C85115 | 28411 ASCENT WAY SANTA CLARITA, CA 91350 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2026 | Corrections Issued | WILBER ROSALES |
| METHANE-Barrier | 3/4/2026 | Approved | WILBER ROSALES |
| METHANE-Subgrade | 3/4/2026 | Approved | WILBER ROSALES |
| Footing/Foundation/Slab | 3/16/2026 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 4/14/2026 | Partial Approval | WILBER ROSALES |
| BUILDING-Rough-Frame | 5/18/2026 | Corrections Issued | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2026 | Approved | WILBER ROSALES |
| Green Building Rough | 5/18/2026 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 5/29/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 5/29/2026 | Not Ready for Inspection | WILBER ROSALES |