10554 N HASKELL AVE 91344
Certificate Information: 10554 N HASKELL AVE 91344
- Application / Permit
- 25014-20000-04579
- Plan Check / Job No.
- B25VN30161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(2). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/1/2026
- Issuing Office
- Current Status
- Issued on 2/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2025 | NGHI SU |
| Corrections Issued | 10/20/2025 | NGHI SU |
| Applicant returned to address corrections | 12/23/2025 | NGHI SU |
| Applicant returned to address corrections | 1/13/2026 | NGHI SU |
| Applicant returned to address corrections | 1/22/2026 | NGHI SU |
| Plan Check Approved | 1/23/2026 | DANIEL YIP |
| Issued | 2/1/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/31/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/31/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 11/12/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 11/17/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Funes Construction Inc; Lic. No.: 1028108-B | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Insulation | 6/8/2026 |
| Gas Test | 6/9/2026 |
| Interior/Exterior Lathing | 6/9/2026 |
| Insulation | 6/9/2026 |
| Drywall Nailing | 6/9/2026 |
| Underground Mechanical | 6/9/2026 |
| BUILDING-Rough-Frame | 6/9/2026 |
Inspection Request History
| Pre-Inspection | 2/10/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 4/10/2026 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 4/16/2026 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 4/16/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 5/21/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 5/21/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| MERV13>=Rough | 5/21/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Special/Order Compliance | 5/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/28/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/28/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/2/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/2/2026 | Partial Approval | CHRISTOPHER ROJAS |