6701 N MATILIJA AVE 91405
Certificate Information: 6701 N MATILIJA AVE 91405
- Application / Permit
- 25014-20000-04562
- Plan Check / Job No.
- B25VN30030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED ADDITIONS AND REMODEL TO (E) 1-STORY SFD W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/12/2026
- Issuing Office
- Current Status
- Issued on 2/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2025 | RAPHAEL ROSAS |
| Assigned to Zoning Architect | 10/23/2025 | LINGHUI YU |
| Corrections Issued | 10/31/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 11/5/2025 | STEVEN KIM |
| Plan Check Approved | 2/10/2026 | RAPHAEL ROSAS |
| Issued | 2/12/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/12/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/12/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2026 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 1/29/2026 | LINGHUI YU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/16/2026 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 3/18/2026 | Partial Approval | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 3/27/2026 | Partial Approval | MICHAEL CORTEZ |
| Special/Order Compliance | 3/27/2026 | Corrections Issued | MICHAEL CORTEZ |
| Footing/Foundation/Slab | 4/22/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2026 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/1/2026 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/1/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/1/2026 | Approved | VINCENT HANLEY |
| Sewer | 6/1/2026 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 6/2/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 6/10/2026 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2026 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/10/2026 | Not Ready for Inspection | VINCENT HANLEY |