9636 S HARVARD BLVD 90047
Certificate Information: 9636 S HARVARD BLVD 90047
- Application / Permit
- 25014-20000-04516
- Plan Check / Job No.
- B25VN29716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, ADDITION TO EX. SINGLE FAMILY DWELLING FOR NEW BEDROOM AND BATHROOM ALL WORK PER WFPP
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2025 | ROSENDO MEDINA |
| Corrections Issued | 10/8/2025 | ROSENDO MEDINA |
| Plan Check Approved | 10/17/2025 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/17/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | SALVADOR MARTINEZ |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/14/2025 | XOCHITL ARQUIETA |
| Sewer availability | Cleared | 10/14/2025 | XOCHITL ARQUIETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2025 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2025 | Conditional Approval | GEM DE OCAMPO |
| Footing/Foundation/Slab | 10/22/2025 | Corrections Issued | SALVADOR MARTINEZ |
| METHANE-Barrier | 10/22/2025 | Approved | SALVADOR MARTINEZ |
| METHANE-Subgrade | 10/22/2025 | Approved | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/27/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/7/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/12/2025 | Partial Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/13/2025 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 11/19/2025 | Partial Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 12/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 12/31/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 1/29/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 1/30/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| METHANE-Rough | 1/30/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/3/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 2/3/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/3/2026 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 2/5/2026 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 2/5/2026 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 2/9/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/18/2026 | Approved | MICHAEL LEWIS |
| Shower Pan | 2/18/2026 | Approved | MICHAEL LEWIS |
| Final | 3/19/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 3/19/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/19/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 3/19/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/16/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/16/2026 | Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 4/16/2026 | Approved | SALVADOR MARTINEZ |
| Final | 4/17/2026 | OK to Issue CofO | SALVADOR MARTINEZ |