17469 W BULLOCK ST 91316
Certificate Information: 17469 W BULLOCK ST 91316
- Application / Permit
- 25014-20000-04510
- Plan Check / Job No.
- B25VN29690
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF GARAGE TO ENLAGE BEDROOM. ADDITION TO ENLARGE GARAGE, ADD PATIO COVER, ADD NEW BEDROOM, ADD TWO BATHROOMS, AND ATTACHED PATIO COVER.
- Permit Issued
- Issued on 11/14/2025
- Issuing Office
- Current Status
- CofO Issued on 4/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2025 | JEROME MAGAT PALMA |
| Corrections Issued | 10/18/2025 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 10/21/2025 | APPLICANT |
| Plan Check Approved | 11/14/2025 | HAYATO TSUCHIYA |
| Issued | 11/14/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | MORRIS JACKSON |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
| CofO Issued | 4/18/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/18/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/20/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 10/20/2025 | STEVE MELGAR |
| ZI | Cleared | 10/20/2025 | STEVEN WECHSLER |
| Watercourse | Cleared | 11/5/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/20/2025 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 11/20/2025 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Not Ready for Inspection | JON MCHUGH |
| Insulation | 11/25/2025 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | JON MCHUGH |
| Green Building Rough | 12/1/2025 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 12/1/2025 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 12/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 12/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 12/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Deputy Wood Construction | 12/18/2025 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 12/29/2025 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 12/29/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | MORRIS JACKSON |
| Gas Test | 12/29/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 12/29/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/2/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/7/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Shower Pan | 1/7/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/8/2026 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/9/2026 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/12/2026 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 1/12/2026 | Approved | MORRIS JACKSON |
| Insulation | 1/12/2026 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/16/2026 | Approved | MORRIS JACKSON |
| Drywall Nailing | 1/16/2026 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/16/2026 | Approved | MORRIS JACKSON |
| Final | 3/6/2026 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 3/6/2026 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 3/6/2026 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 3/6/2026 | Corrections Issued | MORRIS JACKSON |
| Final | 3/11/2026 | OK to Issue CofO | MORRIS JACKSON |
| Smoke Detectors | 3/11/2026 | Approved | MORRIS JACKSON |