6722 N KATHERINE AVE 91405

Certificate Information: 6722 N KATHERINE AVE 91405

Application / Permit
25014-20000-04443
Plan Check / Job No.
B25VN29163
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL
Permit Issued
Issued on 2/4/2026
Issuing Office
Current Status
CofO in Progress on 5/15/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/2/2025 APPLICANT
Assigned to Plan Check Engineer 10/8/2025 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/9/2025 SEWADA ZADOORIAN MILAGARDI
Building Plans Picked Up 10/15/2025 APPLICANT
Plan Check Approved 2/4/2026 ISIS ARGUETA
Issued 2/4/2026 APPLICANT
CofO in Progress 5/15/2026 VINCENT HANLEY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/30/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/30/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/30/2025 BIAINA HARITUNIAN
CPC Cleared 2/3/2026 NATHALY DE LA PAZ
HPOZ Cleared 2/3/2026 NATHALY DE LA PAZ
ZI Cleared 2/3/2026 NATHALY DE LA PAZ
ZI Cleared 2/3/2026 NATHALY DE LA PAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/5/2026 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/6/2026 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 2/11/2026 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 2/23/2026 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 2/23/2026 Approved VINCENT HANLEY
Green Building Rough 2/23/2026 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/23/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/16/2026 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2026 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 3/16/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 3/16/2026 Approved CHRISTOPHE COCHRAN
Wood Frame 3/16/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/19/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Approved VINCENT HANLEY
PLUMBING-Rough 3/19/2026 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Approved VINCENT HANLEY
Insulation 3/23/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/23/2026 Partial Approval VINCENT HANLEY
Drywall Nailing 3/26/2026 Corrections Issued MICHAEL CORTEZ
Shower Pan 3/26/2026 Approved MICHAEL CORTEZ
Special/Order Compliance 3/26/2026 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 4/1/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/1/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/14/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 5/14/2026 Approved VINCENT HANLEY
Final 5/14/2026 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/14/2026 Approved VINCENT HANLEY
Green Building Rough 5/14/2026 Approved VINCENT HANLEY
HVAC-Final 5/14/2026 Approved VINCENT HANLEY
PLUMBING-Final 5/14/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/14/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/14/2026 Approved VINCENT HANLEY