7649 N PASO ROBLES AVE 91406

Certificate Information: 7649 N PASO ROBLES AVE 91406

Application / Permit
25014-20000-04439
Plan Check / Job No.
B25VN29157
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached garage conversion to ADU w/addition per GC 66323(a)(1)
Permit Issued
Issued on 11/17/2025
Issuing Office
Current Status
CofO Issued on 6/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2025 APPLICANT
Assigned to Plan Check Engineer 10/6/2025 DAVID CASTILLO
Corrections Issued 10/7/2025 DAVID CASTILLO
Plan Check Approved 11/12/2025 DAVID CASTILLO
Issued 11/17/2025 APPLICANT
CofO in Progress 5/22/2026 JENNIFER RABUCHIN
Permit Finaled 6/4/2026 RUBEN SALAS
CofO Issued 6/4/2026 RUBEN SALAS
Permit Finaled 6/4/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/22/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/22/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/23/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/23/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 11/6/2025 GEVORK KARAPETYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2025 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/17/2025 Partial Approval GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 12/18/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/22/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 12/22/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 1/12/2026 Conditional Approval GAREN HAYRAPETYAN
HVAC-Rough 1/12/2026 Approved GAREN HAYRAPETYAN
Insulation 1/12/2026 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 1/12/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/20/2026 Approved VINCENT HANLEY
Drywall Nailing 1/20/2026 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Approved VINCENT HANLEY
Green Building Rough 1/20/2026 Approved VINCENT HANLEY
HVAC-Rough 1/20/2026 Approved VINCENT HANLEY
Insulation 1/20/2026 Not Ready for Inspection VINCENT HANLEY
Insulation 1/23/2026 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 1/23/2026 Approved MICHAEL CORTEZ
Shower Pan 1/23/2026 Approved MICHAEL CORTEZ
Drywall Nailing 1/27/2026 Approved MICHAEL CORTEZ
ELECTRICAL-Final 4/8/2026 Corrections Issued KIRK SANDERS
Final 4/8/2026 Corrections Issued KIRK SANDERS
Green Building Final 4/8/2026 Approved KIRK SANDERS
HVAC-Final 4/8/2026 Approved KIRK SANDERS
PLUMBING-Final 4/8/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Required KIRK SANDERS
Smoke Detectors 4/8/2026 Approved KIRK SANDERS
ELECTRICAL-Final 4/23/2026 Approved JENNIFER RABUCHIN
Final 4/23/2026 OK to Issue CofO JENNIFER RABUCHIN
Final 5/22/2026 Partial Approval JENNIFER RABUCHIN