16501 W HAYNES ST 91406
Certificate Information: 16501 W HAYNES ST 91406
- Application / Permit
- 25014-20000-04435
- Plan Check / Job No.
- B25VN29139
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMODEL AND CONVERSION OF (E) DETACHED GARAGE TO KEEP 1'-0" WALL/FOOTING WITH ADDITIONS TO CREATE A (N) DETACHED 2-STORY ACCESSORY DWELLING UNIT (ADU # 1) TO COMPLY WITH GCS 66323(a)(4) PER ENGINEERING. NFPA-13D FIRE SPRINKLER THRU-OUT
- Permit Issued
- Issued on 12/24/2025
- Issuing Office
- Current Status
- Issued on 12/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/2/2025 | APPLICANT |
| Assigned to Zoning Architect | 10/9/2025 | RONALD GREENE |
| Assigned to Plan Check Engineer | 10/16/2025 | ALFRED RAMIREZ |
| Corrections Issued | 10/22/2025 | ALFRED RAMIREZ |
| Quality Review Completed | 10/31/2025 | STEVEN KIM |
| Building Plans Picked Up | 11/3/2025 | APPLICANT |
| Applicant returned to address corrections | 12/2/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 12/24/2025 | ALFRED RAMIREZ |
| Issued | 12/24/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/3/2025 | TONY CHIANG |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2025 | TONY CHIANG |
| Sewer availability | Cleared | 11/3/2025 | TONY CHIANG |
| Low Impact Development (LID) | Cleared | 11/4/2025 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | DERRICK MAGEE |
| ZI | Cleared | 12/5/2025 | ASHLEY RODARTE |
| Zoning Plan Check | Cleared | 12/19/2025 | Ronald Greene |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2026 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 3/6/2026 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 3/10/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 3/10/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 3/10/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 3/12/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/12/2026 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/19/2026 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 4/6/2026 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2026 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Not Ready for Inspection | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 4/30/2026 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2026 | Partial Approval | KIRK SANDERS |
| Sewer | 4/30/2026 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| Shower Pan | 5/6/2026 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 5/18/2026 | Approved | MICHAEL CORTEZ |
| PLUMBING-Rough | 5/18/2026 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 5/22/2026 | Corrections Issued | MICHAEL CORTEZ |
| Shower Pan | 5/22/2026 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 5/29/2026 | Approved | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 5/29/2026 | Approved | MICHAEL CORTEZ |
| Insulation | 6/3/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 6/8/2026 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 6/8/2026 | Approved | GAREN HAYRAPETYAN |