13500 W GOLETA ST 91331

Certificate Information: 13500 W GOLETA ST 91331

Application / Permit
25014-20000-04381
Plan Check / Job No.
B25VN28593
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED NEW BEDRM/BATH/CLOSET & KITCHEN ADDITIONS AT REAR. PROPOSED INT REMODEL W/ NEW BATHRM & HALLWAY TO ADDN. REMODEL EX BEDRM, CONVERT EX CLOSETS INTO A BATHRM, EX BATHRM INTO HALLWAY, REMOVE WALL BETWEEN EX KITCHN & LIVING ROOM TO CREATE ONE OPEN LIVING ROOM PER PLAN. NFPA 13D SPRINKLERS REQUIRED. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 10/22/2025
Issuing Office
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2025 APPLICANT
Assigned to Plan Check Engineer 10/3/2025 HAYATO TSUCHIYA
Corrections Issued 10/4/2025 HAYATO TSUCHIYA
Building Plans Picked Up 10/8/2025 APPLICANT
Applicant returned to address corrections 10/15/2025 SAMUEL GONZALEZ
Plan Check Approved 10/22/2025 NAREG ATARIAN
Issued 10/22/2025 APPLICANT
CofO in Progress 5/29/2026 MICHEL ABAJAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/21/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/21/2025 BIAINA HARITUNIAN
Sewer availability Cleared 10/21/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 1250 W GLENOAKS BLVD E355      GLENDALE, CA 91201

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/8/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 12/10/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 12/10/2025 Approved MICHEL ABAJAN
METHANE-Barrier 12/10/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 12/10/2025 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 12/22/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/22/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Corrections Issued MICHEL ABAJAN
Deputy Wood Construction 1/8/2026 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/21/2026 No Access for Inspection MICHEL ABAJAN
Green Building Rough 1/21/2026 No Access for Inspection MICHEL ABAJAN
MERV13>=Rough 1/21/2026 No Access for Inspection MICHEL ABAJAN
METHANE-Rough 1/21/2026 No Access for Inspection MICHEL ABAJAN
Verify Sprinkler Sign Off 1/21/2026 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 2/4/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/12/2026 Approved MICHEL ABAJAN
Gas Test 3/12/2026 Approved MICHEL ABAJAN
Green Building Rough 3/12/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/12/2026 Approved MICHEL ABAJAN
MERV13>=Rough 3/12/2026 Approved MICHEL ABAJAN
METHANE-Rough 3/12/2026 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 3/12/2026 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/12/2026 Approved MICHEL ABAJAN
Insulation 3/17/2026 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/17/2026 Approved MICHEL ABAJAN
Drywall Nailing 4/2/2026 Approved MATTHEW NELSON
ELECTRICAL-Final 5/29/2026 Approved MICHEL ABAJAN
Final 5/29/2026 OK to Issue CofO MICHEL ABAJAN
Green Building Final 5/29/2026 Approved MICHEL ABAJAN
HVAC-Final 5/29/2026 Approved MICHEL ABAJAN
MERV13>=Final 5/29/2026 Approved MICHEL ABAJAN
PLUMBING-Final 5/29/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/29/2026 Approved MICHEL ABAJAN