6839-6841 N CALVIN AVE 91335

Certificate Information: 6839-6841 N CALVIN AVE 91335

Application / Permit
25014-20000-04376
Plan Check / Job No.
B25VN28579
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 2-STORY (32'-6" X 18' IRR SHAPE) ATTACHED ACCESSORY DWELLING UNIT PER GOVT. CODE 66323(a)(1).
Permit Issued
Issued on 11/3/2025
Issuing Office
Valley
Current Status
CofO Issued on 5/21/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2025 APPLICANT
Assigned to Plan Check Engineer 10/2/2025 VAHAN JIVALAGIAN
Assigned to Zoning Architect 10/2/2025 LY CHEA
Corrections Issued 10/4/2025 VAHAN JIVALAGIAN
Quality Review Completed 10/6/2025 OMID HEDAYAT
Building Plans Picked Up 10/8/2025 APPLICANT
Plan Check Approved 11/3/2025 VAHAN JIVALAGIAN
Issued 11/3/2025 APPLICANT
CofO in Progress 4/30/2026 ARUTYUN MADATYAN
Permit Finaled 5/21/2026 JOHN JANSON
CofO Issued 5/21/2026 JOHN JANSON
Permit Finaled 5/21/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/14/2025 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 10/14/2025 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 10/14/2025 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 10/14/2025 VLADIMIR ARUTYUNYAN
Zoning Plan Check Cleared 10/23/2025 LY CHEA

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/6/2025 Partial Inspection ARUTYUN MADATYAN
Underground Mechanical 11/10/2025 Approved JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 11/13/2025 Corrections Issued JUAN ALVARADO
Excavation/Setback/Form/Re-Bar 11/25/2025 Conditional Approval JUAN ALVARADO
BUILDING-Rough-Frame 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Rough 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2026 Partial Approval ARUTYUN MADATYAN
Wood Frame 1/22/2026 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 1/28/2026 Corrections Issued JUAN ALVARADO
Interior/Exterior Lathing 1/30/2026 Approved JUAN ALVARADO
BUILDING-Rough-Frame 2/19/2026 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 2/19/2026 Corrections Issued ARUTYUN MADATYAN
HVAC-Rough 2/19/2026 Approved ARUTYUN MADATYAN
PLUMBING-Rough 2/19/2026 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 2/24/2026 Approved JUAN ALVARADO
HVAC-Rough 2/24/2026 Approved JUAN ALVARADO
PLUMBING-Rough 2/24/2026 Not Ready for Inspection JUAN ALVARADO
BUILDING-Rough-Frame 2/26/2026 Approved JUAN ALVARADO
Green Building Rough 2/26/2026 Approved JUAN ALVARADO
PLUMBING-Rough 2/26/2026 Approved JUAN ALVARADO
Insulation 3/2/2026 Approved JUAN ALVARADO
Sewer 3/2/2026 Approved JUAN ALVARADO
Shower Pan 3/2/2026 Approved JUAN ALVARADO
Underground Mechanical 3/2/2026 Approved JUAN ALVARADO
Drywall Nailing 3/5/2026 Approved DAVID FASTIGGI
Interior/Exterior Lathing 3/11/2026 Corrections Issued JUAN ALVARADO
Interior/Exterior Lathing 3/17/2026 Approved JUAN ALVARADO
Final 4/27/2026 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 4/27/2026 Approved JUAN ALVARADO
Green Building Final 4/27/2026 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Approved JUAN ALVARADO
Smoke Detectors 4/27/2026 Approved JUAN ALVARADO
ELECTRICAL-Final 4/30/2026 Approved ARUTYUN MADATYAN
Final 4/30/2026 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 4/30/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 4/30/2026 Approved ARUTYUN MADATYAN