3238-3238 1/2 S CORINTH AVE 90066
Certificate Information: 3238-3238 1/2 S CORINTH AVE 90066
- Application / Permit
- 25014-20000-04359
- Plan Check / Job No.
- B25VN28452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE 1-STORY SFD EXCEPT (E) 12" X 12" FOOTING TO REMAIN & ADD 2-STORY SFD W/ ATTACHED GARAGE & 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(e) [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 1/26/2026
- Issuing Office
- Metro
- Current Status
- Issued on 1/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/26/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2025 | EDWARD MEHRABIAN |
| Assigned to Zoning Architect | 10/2/2025 | ERIC ROMERO |
| Corrections Issued | 10/5/2025 | EDWARD MEHRABIAN |
| Quality Review Completed | 10/9/2025 | OMID HEDAYAT |
| Building Plans Picked Up | 10/15/2025 | APPLICANT |
| Plan Check Approved | 1/6/2026 | NILOOFAR MEHRAIN |
| Issued | 1/26/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/20/2025 | STEVE MELGAR |
| Construction near power lines | Cleared | 10/21/2025 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 10/21/2025 | STEVE MELGAR |
| Specific Plan | Cleared | 10/22/2025 | RICHARD WOO |
| Zoning Plan Check | Cleared | 11/17/2025 | ERIC ROMERO |
| GPI Written Notices | Cleared | 1/6/2026 | EDWARD MEHRABIAN |
| Grading Pre-Inspection | Cleared | 1/6/2026 | EDWARD MEHRABIAN |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 8537 PICKFORD ST LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Consulting Llc; Lic. No.: 942979-B | 8537 PICKFORD STREET LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/5/2026 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/5/2026 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/10/2026 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2026 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 5/4/2026 | Conditional Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/7/2026 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/7/2026 | Approved | EUGENE CASSIDY |
| Green Building Rough | 5/7/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 5/7/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 5/7/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/15/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 5/15/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 5/15/2026 | Approved | ANTHONY EGSON |
| MERV13>=Rough | 5/15/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/28/2026 | Approved | ANTHONY EGSON |
| Insulation | 6/2/2026 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 6/2/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/8/2026 | Approved | KIRK SANDERS |
| Drywall Nailing | 6/8/2026 | Approved | KIRK SANDERS |
| Final | 6/8/2026 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 6/8/2026 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/8/2026 | Approved | KIRK SANDERS |
| Special/Order Compliance | 6/10/2026 | Approved | KIRK SANDERS |