19809 W ARCHWOOD ST 91306

Certificate Information: 19809 W ARCHWOOD ST 91306

Application / Permit
25014-20000-04358
Plan Check / Job No.
B25VN28443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) Detached Garage/Recreation Room into an Accessory Dwelling Unit w/ addition per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
CofO in Progress on 6/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2025 APPLICANT
Assigned to Plan Check Engineer 10/1/2025 AMY GUEVARRA
Corrections Issued 10/2/2025 AMY GUEVARRA
Applicant returned to address corrections 11/7/2025 AMY GUEVARRA
Plan Check Approved 11/10/2025 AMY GUEVARRA
Issued 11/12/2025 APPLICANT
CofO in Progress 6/30/2026 ALEXANDER HANDY

Permit Application Clearance Information

Address approval Cleared 10/3/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 10/3/2025 CINDY QI
Roof/Waste drainage to street Cleared 10/3/2025 CINDY QI
Sewer availability Cleared 10/3/2025 CINDY QI
Construction near power lines Cleared 11/6/2025 GEVORK KARAPETYAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Dream Home Design & Build Inc; Lic. No.: 1092321-B       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 12/15/2025 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 1/29/2026 Approved JUAN ALVARADO
PLUMBING-Rough 1/29/2026 Corrections Issued JUAN ALVARADO
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Partial Approval GEVORK IPCHYAN
Interior/Exterior Lathing 3/2/2026 Approved DAVID FASTIGGI
PLUMBING-Rough 3/2/2026 Approved DAVID FASTIGGI
Shower Pan 3/2/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 3/12/2026 Partial Approval DAVID FASTIGGI
Interior/Exterior Lathing 3/12/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 3/18/2026 Partial Approval DAVID FASTIGGI
Insulation 3/25/2026 Corrections Issued DAVID FASTIGGI
Insulation 4/1/2026 Approved DAVID FASTIGGI
Drywall Nailing 4/7/2026 Approved DAVID FASTIGGI
HVAC-Rough 4/7/2026 Approved DAVID FASTIGGI
BUILDING-Rough-Frame 4/8/2026 Approved DAVID FASTIGGI
Green Building Rough 4/8/2026 Approved DAVID FASTIGGI
Final 6/8/2026 Corrections Issued ALEXANDER HANDY
Green Building Final 6/8/2026 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 6/8/2026 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 6/8/2026 Approved ALEXANDER HANDY
ELECTRICAL-Final 6/29/2026 Approved ALEXANDER HANDY
Final 6/29/2026 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 6/29/2026 Approved ALEXANDER HANDY
PLUMBING-Final 6/29/2026 Approved ALEXANDER HANDY